SPML Infra secured Rs. 165.41 crore contract from RRVPNL for 400 kV grid substation construction in Kota, Rajasthan.
The project includes supply, erection, testing and commissioning of substation with 500 MVA transformer and associated infrastructure.
Order execution period is 24 months and falls within company's normal course of business operations.
Project supports Rajasthan's energy transition and strengthens SPML's power vertical portfolio.