Authority: Supreme Court of India
Order Date: 17-11-2026
Case Overview
- Petitioners: Bhushan Pramod Papinwar & Anr.; Respondent: M/s Sandeep Constructions.
- The petition arose from the impugned final judgment and order dated 06‑02‑2026 in MFA No. 6353/2025 passed by the High Court of Karnataka, Bengaluru.
- Two applications were filed: (i) condonation of delay in filing the Special Leave Petition (Civil); (ii) exemption from filing a copy of the impugned judgment.
- The matter was heard before a bench of Hon’ble Mr. Justice Aravind Kumar and Hon’ble Mr. Justice Vipul M. Pancholi.
Final Outcome
- The Court condoned the delay in filing the petition.
- It found no sufficient ground to entertain the petition and dismissed the Special Leave Petition.
- Any pending applications, if any, were ordered to stand disposed of.
Topics: Legal Dispute, Supreme Court Judgment, Construction Sector