Date: 04 July 2026

Operational / Strategic Disclosures

SWELECT Energy Systems Limited successfully commissioned a 4.40 MW solar power plant on 03 July 2026.

The plant is located at V. Muthulingapuram Village, Virudhunagar Taluk, Virudhunagar District, Tamil Nadu.

The plant is connected to the 33/11KV Naranapuram SS at the 33 KV level.

The energy generated will be supplied to a group of consumers under a 3rd Party Power Sale model.

The power sale will be conducted through Intra State Open Access in the state of Tamil Nadu.

KMP / Board / Auditor Changes

Not Specified

Dividend Declaration or Non-Declaration

Not Specified

Board Meeting Outcomes

Not Specified

Financial Results

Not Specified

Auditor’s Report

Not Specified

Disinvestment / Strategic Actions

Not Specified