Authority: Supreme Court of India
Order Date: 10-09-2026
Case Overview
- Parties: Tashee Land Developers Pvt Ltd & Anr. (Appellant) versus Sunil Nautiyal & Anr. (Respondent).
- Civil Appeal Diary No. 4644 of 2025 was pending restoration after a delay of 190 days in filing the restoration application (IA No. 66522/2026).
- The matter was heard on 10‑09‑2026 before Hon'ble Mr. Justice Nongmeikapam Kotiswar Singh, sitting in chamber.
- Counsel for the appellant was Mr. Gaurav, AOR; no counsel was listed for the respondent.
Final Outcome
1. The Court condoned the 190‑day delay in filing the restoration application.
2. The application for restoration of the civil appeal was allowed.
3. Civil Appeal Diary No. 4644 of 2025 is restored to its file and original number.
4. Consequently, the miscellaneous application (DIARY NO(s). 60642/2025) stands disposed of.
Topics: Civil Appeal Restoration, Delay Condonation, Supreme Court Order