Date: November 11, 2026
Board Meeting Outcomes
The Board of Directors at its meeting held on November 11, 2026 approved a significant capital investment in energy infrastructure:
- Investment Approved: ₹11,871 crore for a 1,800 MW Pumped Storage Project at Shirwata, Maharashtra
- Project Timeline: 51 months for completion
- Financing Structure: 75% debt financing and 25% equity financing
Project Details
- Project Type: Pumped Storage Hydro Project (PSP)
- Capacity Addition: 1,800 MW
- Location: Shirwata, Maharashtra
Strategic Rationale
The Pumped Storage Project will be instrumental in:
- Enabling Renewable Energy Round the Clock (RE-RTC) applications
- Facilitating energy shifting capabilities
- Contributing to decarbonization of hard-to-abate industries
Current Capacity Context
- Existing Capacity: 16.9 GW overall
- Capacity Utilization: Operating at optimum level