Tata Power commissioned 400 kV Tanda–Gonda and Gonda–Basti double circuit lines spanning 154 Ckm in Uttar Pradesh.
All EHV transmission lines under SEUPPTCL project are now complete, comprising 17 corridors totalling 1,517 circuit kilometres.
Total operational transmission network expands to 5,466 Ckm, with 1,863 Ckm additionally under construction.
The network enables evacuation of over 4,000 MW of thermal power, enhancing grid stability and energy security in UP.