Summary of Key Information:
Reporting Period (Quarter/Year): Not Specified
Nature of Filing / Announcement: Outcome of Board Meeting - Acquisition Approval
Date of Board Meeting / Approval: October 19, 2026
Audit Opinion: Not Specified
Auditor's Comment: Not Specified
Key Financial Highlights:
Standalone Results: Not Specified
Consolidated Results: Not Specified
Corporate Actions:
- Approved acquisition of 49% equity stake in NOPL Pace Green Energy Private Limited
- Execution of Share Purchase Agreement and Shareholders' Agreement approved
- Cash consideration of up to ₹20 crore for 49% equity share capital
- Investment structured to provide financial and project management control
- Flexibility to increase shareholding potentially up to 100% subject to terms and approvals
Other Significant Information:
Target Company Details:
- Name: NOPL Pace Green Energy Private Limited
- Incorporation Date: April 25, 2024
- Registered Address: Shop No. 11, Ground Floor, Plot No. 44, CTS 950, Kothrud, Pune City, Maharashtra 411038
- Business: Generation of Power, specifically solar power generation projects
Financial Status (Audited FY 2025-26):
- Total Revenue Including Other Income: ₹1,046.85 thousand
- Total Expenses: ₹1,267.11 thousand
- Profit before Tax: (₹220.26) thousand
- Tax expenses: ₹0
- Profit after Tax: (₹220.26) thousand
- Net Worth: (₹120.26) thousand
- Paid up share capital: ₹100,000
Project Details:
- Developing aggregated solar power portfolio of approximately 990 MW (AC)
- Project under Pradhan Mantri Kisan Urja Suraksha evam Utthan Mahabhiyan (PM-KUSUM) Scheme
- Project cost: Approximately ₹3,900 crore
- Locations: Across Maharashtra
- 25-year Power Purchase Agreement executed with Maharashtra State Electricity Distribution Company Limited (MSEDCL)
- Fixed tariff: ₹3.10 per unit
- Project debt sanctioned by reputed financial institution
- Target company at advanced stage of development
Strategic Rationale:
- Entry into renewable power generation business
- Participation in large solar portfolio with long-term contracted power offtake arrangement
- Leveraging Transrail's capabilities in engineering, procurement, and project management
- Opportunities across value chain including project implementation and long-term ownership returns
- Diversification beyond EPC business into renewable power generation
- Potential for recurring earnings after commissioning
Timeline and Process:
- Acquisition to be completed within 180 days from approval by Target Company's Board of Directors
- Company's further investment will be phased in line with project milestones and debt drawdown
- Upon completion, NOPL Pace Green Energy Private Limited shall become an Associate of the Company