Key Quantitative Figures

  • Total project investment: ₹4,650 Crores
  • Breakdown by business segment:
  • Yarn (Budhni, MP): ₹1,022 Crores
  • Yarn (Dhar, MP): ₹1,660 Crores
  • Sheeting: ₹1,018 Crores
  • Paper: ₹296 Crores
  • Hybrid Power: ₹654 Crores

Capacity Expansion Details

Yarn Business - Budhni, Madhya Pradesh

  • Capacity addition: 99,840 Spindles
  • Modernization: 48,000 old Spindles being modernized to 70,176 New Spindles on finer counts
  • Replacement: 960 old rotors being replaced with 2,400 new rotors
  • Existing capacity: 746,064 Spindles, 5,424 Rotors & 320 Air Jet
  • Existing utilization: 94% at Budhni facility
  • Completion target: December 31, 2027

Yarn Business - Dhar, Madhya Pradesh

  • New manufacturing facility with capacity: 199,680 spindles
  • Land acquired: 179.2 acres of leasehold land at cost of approximately ₹106.09 Crores
  • Completion target: September 30, 2029

Sheeting Business

  • Expansion through addition of: 336 looms
  • Existing capacity: 504 looms
  • Existing utilization: 58%
  • Completion target: January 31, 2028

Paper Business

  • Capacity enhancement: 28 TPD (Tons Per Day)
  • Existing capacity: 479 TPD
  • Existing utilization: 81%
  • Completion target: March 31, 2028

Renewable Energy

  • 60 MW Hybrid Renewable Energy Project comprising:
  • 60 MW Wind Power
  • 20 MW Solar Power (AC)
  • Existing capacity: 57.3 MW DC peak (Solar)
  • Existing utilization: 100%
  • Completion target: October 31, 2028

Dates and Timing

  • Board Meeting Date: November 02, 2026
  • Meeting Duration: 10:30 A.M. IST to 16:00 P.M. IST

Financing Mode

  • Mode of financing: From Internal Accruals/debt

Rationale and Purpose

The proposed projects are expected to strengthen the Company's existing market position, enhance operational capabilities, support sustainable and environmentally responsible operations, improve energy efficiency and further augment its presence in domestic and international markets.