Financial Performance Highlights
- Revenue: ₹246 crore for H1 FY27, representing a 42% increase compared to the previous year
- EBITDA: ₹23 crore, with corresponding increase in absolute terms but margin percentage declined due to revenue composition
- PAT: ₹8.63 crore, marginally lower than previous year's ₹8.70 crore
- EPS: Marginally lower by 3 paisa compared to previous year
- Finance Cost: ₹8.39 crore for H1 FY27 compared to ₹8.36 crore for H2 FY26, despite significant increase in borrowings
Working Capital and Borrowings
- Total Borrowings: Increased from ₹111 crore at H2 FY26 end to ₹232 crore at H1 FY27 end
- Working Capital Impact: Three primary factors driving increased working capital requirements:
1. Increase in raw material prices (cashew nuts)
2. Logistics delays increasing transit time from 35-45 days to 110-112 days
3. Later Diwali due to Adhik Maas requiring additional finished goods inventory
Margin Structure Explanation
Management explained the unique margin structure of the cashew business:
- Revenue comprises raw cashew nut price plus fixed value addition margin (approximately ₹27/kg)
- Operating costs are approximately ₹20/kg
- EBITDA per kg remains stable at ₹7/kg regardless of raw material price fluctuations
- As raw material prices increase, EBITDA percentage declines while absolute EBITDA per kg remains constant
Operational Updates
- Current Capacity: 140 metric tons per day shelling capacity
- Certification: FSSC 22,000 certified operations
- Sourcing Strategy: Buying directly from African origins through merchant traders in UAE, Singapore, or Europe
- Market Focus: Targeting Middle East exports alongside domestic market, with merchant exports already commenced
Expansion Plans
On 2nd November 2026, the board approved a major expansion project:
- Shelling Capacity: Increase from 140 to 200 metric tons per day (60 metric ton addition)
- New Facilities: Cardanol production unit
- Infrastructure: Staff housing colony
- Project Cost: ₹100 crore for manufacturing unit and land, plus ₹14 crore for staff housing colony (Total: ₹114 crore)
- Timeline: 30 months for completion
- Funding: Through internal accruals and debt
Project Delays and Updates
- CNSL Oil Plant: Expected to commence operations by mid or end of December 2026 (delayed due to technical modifications)
- Solar Plant: Expected to commence by mid or end of December 2026 (delayed due to approval delays from substation and rains affecting civil work)
- Utilization: Expected to reach full input levels of 100 tons per day (from 140 metric tons shelling capacity) by year-end
Global Market Context
- India: Largest consumer with 30% market share (300,000 tons)
- Europe: Second largest with 25% market share (300,000 tons), currently affected by economic challenges
- United States: Third largest with 140,000 metric tons
- China: Fourth largest with 110,000 tons, predominantly served by Vietnam
- Logistics Impact: Strait of Hormuz closure and Bab el-Mandeb inclusion in conflict significantly increased transit times and costs
Management Outlook
- Confident in utilizing expanded capacities based on current 95-97% utilization rates
- Targeting 1000 metric ton capacity by 2037 through phased expansions
- Export margins generally lower than domestic market, but exports provide liquidity for higher quality grades
- Realizations currently around ₹735-738 per kg for kernels, influenced by raw cashew prices, shell prices, and packing material costs
Q&A Highlights
- Management acknowledged learning from previous timeline commitments and now providing more conservative project timelines (30 months for new expansion)
- Working capital requirements expected to remain elevated due to continued high cashew prices and logistics challenges
- Long-term debt remains low despite increased working capital borrowings
- Volume data available upon request via email