Financial Performance Highlights
Q2FY27 Performance (Quarter Ended September 2026):
- Turnover: ₹1,463.67 crores
- PAT: ₹55.86 crores
- EPS: ₹8.34
- EBITDA Margin: 7.58%
- PAT Margin: 3.78%
Sequential Comparison (Q2FY27 vs Q1FY27):
- Turnover growth: 30.01% (from ₹1,125.81 crores)
- PAT growth: 389.2% (from ₹11.48 crores)
- EBITDA margin improved from 4.29% to 7.58%
- PAT margin improved from 1.0% to 3.78%
Year-over-Year Comparison (Q2FY27 vs Q2FY26):
- Turnover growth: 24.32% (from ₹1,177.30 crores)
- PAT degrowth: -29.33% (from ₹79.05 crores)
- EBITDA margin declined from 10.92% to 7.58%
- PAT margin declined from 6.63% to 3.78%
- EPS declined from ₹11.80 to ₹8.34
H1FY27 Performance (April-September 2026):
- Turnover: ₹2,589.48 crores
- PAT: ₹67.28 crores
- EPS: ₹10.04
- EBITDA Margin: 6.15%
- PAT Margin: 2.57%
H1FY26 Comparison:
- Turnover: ₹2,182.18 crores
- PAT: ₹130.16 crores
- EBITDA Margin: 9.85%
- PAT Margin: 5.88%
- EPS: ₹19.14
Order Book & Inflow
- Net order book as of September 30, 2026: ₹19,627.92 crores
- Execution timeline: 3 to 3.5 years
- Order inflow during FY27 till September 30, 2026: ₹558.07 crores
- L1 in one project amounting to ₹379.00 crores
- Post-September order win: Times of India Bennett University project worth ₹350+ crores
- FY27 order inflow guidance: ₹4,000 crores
Management Guidance & Commentary
Revenue Guidance:
- FY27: 15% growth guidance maintained
- FY28: 15-20% growth expected
Margin Guidance:
- Q3FY27 and Q4FY27 EBITDA margins expected to be similar to Q2FY27 (7.58%)
- FY28 EBITDA margin guidance: 8.5%-9% (improvement of at least 100 bps)
- Double-digit margins considered unlikely due to ongoing headwinds
NCR Pollution Impact (GRAP Guidelines):
- Construction in NCR currently shut due to pollution control measures
- Expected work loss: 1 to 1.5 months in Q3FY27
- Central Vista project (Delhi) exempt from GRAP guidelines
- Max Hospital project in Gurgaon also exempt
- Expected Q3FY27 revenue impact: ~10% sequential decline
- Q4FY27 expected to be the best quarter
Project-Specific Updates
Central Vista Project:
- Exempt from GRAP construction bans
- October turnover: ₹43 crores
- Expected November turnover: ₹60 crores
- Expected December turnover: ₹60-70 crores
- Q3FY27 expected billing: ₹150 crores
- Q4FY27 expected billing: ₹200+ crores
- Total project value: ₹3,000 crores
- Timeline: ~2 years completion target
CSMT (CST) Railway Station Project:
- Execution has picked up significantly
- October turnover: ₹80 crores (up from ₹50 crores previously)
- Actual work done: ₹100-110 crores (billing conversion lower due to railway processes)
- Q3FY27 expected billing: ₹150 crores
- Q4FY27 expected billing: ₹200 crores
India Jewellery Park Mumbai:
- Notice to proceed not yet received from client
- Client sorting internal permissions and matters
- No turnover expected in Q3FY27
- Even after notice received, actual work will take ~3 months to start
- Land cleanup pending by client
- Earthwork ban in Mumbai causing additional delays
- Cancellation not considered a possibility
- Contract type not specified in disclosure
Other Projects:
- Hospital project in Gurgaon: Exempt from GRAP, expected ₹50 crores in Q3FY27
Regional Revenue Breakdown
- Q2FY27 total revenue: ₹1,463 crores
- NCR contribution: ~₹520 crores (approximately 35.5%)
- Q1FY27 NCR contribution: ~₹350 crores (approximately 31% of ₹1,125 crores)
Cost Structure & Efficiency
Staff Costs:
- Q2FY27 staff cost: ₹133 crores (significant increase)
- Increase due to annual increments and PF law changes
- EPF wage ceiling increased from ₹15,000 to ₹25,000
- 85% of labor force and staff now under PF ambit
- Absolute staff cost increased by ₹12.5 crores
- PF outlays increased by ~₹3 crores in September
- Costs not expected to decrease, but should decline as percentage of revenue
Supply Chain Challenges:
- Planning timelines extended from 2-3 weeks to 5-8 weeks for materials
- Electromechanical materials (chillers, panels, transformers) facing longest delays
- Middle East war impacting supply chains
- Better planning implemented to mitigate disruptions
Labor Challenges:
- Significant skill shortage in construction workforce
- 35-40% labor cost increase in UP
- 50% of clients have agreed to labor escalation clauses
- Material costs higher by 4-5 percentage points
- Government intervention needed for skill development
Capital Expenditure
- FY27 capex guidance: ₹300 crores
- FY26 actual capex: ₹220 crores
- Being conservative due to cyclical nature of business and global uncertainties
- Current equipment considered sufficient for order book execution
Other Income
- H1FY27 other income: Not quantified
- Expected to remain at similar levels going forward
- Improved cash balance supporting other income
Depreciation Trend
- Depreciation continues to increase
- Management considering efficiency improvements rather than significant additional capex
- Conservative approach due to business cyclicality
Geographic Expansion
- Currently 24% of order book from South India
- 15% from East India
- Actively bidding in Bangalore, Hyderabad, and Mumbai
- Looking to grow presence in these regions
Pipeline Projects
- Total pipeline: ₹5,000-6,000 crores
- ₹1,500 crores of private sector projects
- Significant public sector bidding opportunities
Mobilization Advances
- Mobilization advance: ₹939 crores
- Retention money: ₹437 crores
- Unbilled revenue: ₹987 crores
- Utilization rate: 32%
Taxation
- Normal tax rate: 25.17%
- Effective tax rate for Q2FY27: 29.02%
Participant List
Analysts from Nuvama Group, Dolat Capital, ICICI Securities, Counter Cyclical PMS, JM Financial, Unique PMS, and other institutions participated in the call.