Key Quantitative Figures & Operational Highlights

Swarnagiri Gold Mine (formerly Jonnagiri, Andhra Pradesh)

  • Q2 FY27 Gold Production: 135 kg (up from 89 kg in Q1 FY27)
  • Production Rate: Reached ~40 kg per month, targeting 45 kg/month
  • Gold Recovery: 90-95% recovery rate in gold circuit
  • H1 FY27 Standalone Profit: ~₹80 Cr from revenue of ~₹160 Cr (50% PAT margin)
  • H1 FY27 Deccan Share of Profit: ₹20.57 Cr
  • Refined Bullion Sold in H1: 109 kg
  • Inventory Value: ₹134 Cr (includes run-of-mine ore, gold in circuit, doré, and bullion valued at production cost)
  • Inventory Quantity: 133 kg of doré plus bullion
  • Target Production: 450+ kg for FY27; potential for 1,000 kg/year with new approvals; long-term target of 2 tons/year

Altyn-Tor Gold Project (Kyrgyzstan)

  • Commissioning Date: September 12, 2026
  • First Doré Dispatch: 1.2 kg test consignment sent to refinery
  • Resource Estimate:
  • Stockpiles & tailings: 1.09 tons gold at 0.99 g/t avg grade
  • In-situ resource: 4.5 tons gold at 1.69 g/t avg grade
  • Underground potential: Additional 3 tons at 2.5-3 g/t grade
  • Target Production: 180 kg for FY27; ramp to 300 kg next year; 700-750 kg with underground operations
  • Corporate Structure: Revenue sharing - Kyrgyzaltyn (govt) 17%, Avelum Partners 83% (Deccan 60% of Avelum = 49.8% net revenue share)
  • Winter Operations: 30,000 tons of ROM/semi-processed material available for commissioning

Fundraising

  • Amount Raised: ₹137 Cr (approved in August/September 2026, BSE approvals received recently)
  • Use of Funds: Exploration drilling in Finland gold project, Bhalukona nickel-copper, Spain tungsten, and Mozambique lithium-tantalum projects

Other Gold Projects

  • Finland Gold Project: Planning 1,000-1,500m drilling; targets 700-800 kg/year production with 800 TPD plant; royalty 2.5%, corporate tax 20%
  • Ganajur Gold Project (Karnataka):
  • Resource: 9 tons gold at 3.8 g/t avg grade
  • Supreme Court hearing scheduled for December 1, 2026
  • Previously recommended by state (2010), prior approval from Ministry of Mines (2015), state legal opinion favored lease grant (2017)
  • If approved: 2-3 years to production, target 1 ton/year, EBITDA margins 75-80%

Critical Minerals Projects

  • Bhalukona Nickel-Copper-PGE (India):
  • 2,000m drilling completed; 1.3km mineralized zone
  • Estimated 4M tons at 0.24% Ni equivalent
  • Planning mining application by H1 2027; potential 3,000 TPD plant
  • Target production: 2029 or pilot-scale earlier
  • Logrosán Tungsten Project (Spain):
  • 5,400m drilling completed; all holes intersected economic mineralization
  • Estimated 2.3M tons resource (growing)
  • Zero royalty; corporate tax 25%
  • Mozambique Lithium-Tantalum:
  • 150 km² area; multiple pegmatite zones
  • Planning 1,500-2,000m drilling
  • Potential for 2028 commercialization; royalty <3%

Projects Under Due Diligence

  • Finland Gold Project: 45 km²; 6 tons gold + 9 tons silver resource
  • Brownfield Gold Project: 3.3 tons gold resource, potential to 10+ tons
  • Graphite Project: 1km explored, 10km potential; 94% recovery; flaky graphite for batteries

Financial Performance

  • Q2 FY27 PAT: ₹13.91 Cr (vs ~₹6 Cr previous quarter)
  • H1 FY27 Consolidated Loss: ₹9.28 Cr (despite associate profits)
  • Consolidated Loss Reason: Tier 2 projects and subsidiaries not yet in production

Key Dates & Regulatory References

  • Earnings Call Date: November 20, 2026
  • Kyrgyzstan Commissioning: September 12, 2026
  • Ganajur Supreme Court Hearing: December 1, 2026
  • Fundraising Approval: August 2026 (Board), September 2026 (EGM)
  • SEBI Regulation: Reg. 30 disclosure

Management Commentary & Guidance

  • Swarnagiri: Expect 450-500 kg production in FY27; inventory built for festive season sales
  • Kyrgyzstan: Winter operations ongoing; production clarity expected in 15-20 days
  • Funding Strategy: Future funding through market instruments (debt/equity) or offtake arrangements for critical minerals
  • Promoter Stake: Exploring increase in promoter stake and Kyrgyzstan project stake
  • Gold Price Impact: Current price decline may reduce EBITDA margins from 70% to 65-67%
  • Critical Minerals Contribution: Expected to remain secondary to gold (60% revenue from gold) in medium term

Parties Involved

  • Subsidiaries/Associates: Thriveni Lloyds Swarnagiri, Avelum Partners
  • Partners: Hira Group (26% in Avelum), Medetbek (14% in Avelum), Kyrgyzaltyn (govt partner)
  • Legal Counsel: Engaged senior counsel for Supreme Court case
  • Regulators: SEBI, BSE, Supreme Court of India, Ministry of Mines

Capital Structure Impact

  • No immediate dilution planned; considering offtake arrangements instead of equity dilution for critical minerals
  • Exploring stake increase in Kyrgyzstan project

Cash Flow Implications

  • ₹137 Cr fundraising for exploration
  • Swarnagiri profits not yet distributed as dividends
  • Future capex requirements: ₹400-600 Cr for critical mineral projects

Forward-Looking Statements (Explicitly Disclosed)

  • Kyrgyzstan production targets: 180 kg (FY27), 300 kg (FY28), 700-750 kg (underground)
  • Project commercialization: Mozambique (2028), Bhalukona (2029), others (2029-2030)
  • Ganajur timeline: 2-3 years to production if approved
  • Planned analyst meets before December 15, 2026