Deccan Gold Mines Q2 FY27 Earnings Call Transcript
Earnings & Results
Price while announcement
Current price (CMP)
Tulsian AI News Agent
·
23rd Nov 2026
Key Quantitative Figures & Operational Highlights
Swarnagiri Gold Mine (formerly Jonnagiri, Andhra Pradesh)
- Q2 FY27 Gold Production: 135 kg (up from 89 kg in Q1 FY27)
- Production Rate: Reached ~40 kg per month, targeting 45 kg/month
- Gold Recovery: 90-95% recovery rate in gold circuit
- H1 FY27 Standalone Profit: ~₹80 Cr from revenue of ~₹160 Cr (50% PAT margin)
- H1 FY27 Deccan Share of Profit: ₹20.57 Cr
- Refined Bullion Sold in H1: 109 kg
- Inventory Value: ₹134 Cr (includes run-of-mine ore, gold in circuit, doré, and bullion valued at production cost)
- Inventory Quantity: 133 kg of doré plus bullion
- Target Production: 450+ kg for FY27; potential for 1,000 kg/year with new approvals; long-term target of 2 tons/year
Altyn-Tor Gold Project (Kyrgyzstan)
- Commissioning Date: September 12, 2026
- First Doré Dispatch: 1.2 kg test consignment sent to refinery
- Resource Estimate:
- Stockpiles & tailings: 1.09 tons gold at 0.99 g/t avg grade
- In-situ resource: 4.5 tons gold at 1.69 g/t avg grade
- Underground potential: Additional 3 tons at 2.5-3 g/t grade
- Target Production: 180 kg for FY27; ramp to 300 kg next year; 700-750 kg with underground operations
- Corporate Structure: Revenue sharing - Kyrgyzaltyn (govt) 17%, Avelum Partners 83% (Deccan 60% of Avelum = 49.8% net revenue share)
- Winter Operations: 30,000 tons of ROM/semi-processed material available for commissioning
Fundraising
- Amount Raised: ₹137 Cr (approved in August/September 2026, BSE approvals received recently)
- Use of Funds: Exploration drilling in Finland gold project, Bhalukona nickel-copper, Spain tungsten, and Mozambique lithium-tantalum projects
Other Gold Projects
- Finland Gold Project: Planning 1,000-1,500m drilling; targets 700-800 kg/year production with 800 TPD plant; royalty 2.5%, corporate tax 20%
- Ganajur Gold Project (Karnataka):
- Resource: 9 tons gold at 3.8 g/t avg grade
- Supreme Court hearing scheduled for December 1, 2026
- Previously recommended by state (2010), prior approval from Ministry of Mines (2015), state legal opinion favored lease grant (2017)
- If approved: 2-3 years to production, target 1 ton/year, EBITDA margins 75-80%
Critical Minerals Projects
- Bhalukona Nickel-Copper-PGE (India):
- 2,000m drilling completed; 1.3km mineralized zone
- Estimated 4M tons at 0.24% Ni equivalent
- Planning mining application by H1 2027; potential 3,000 TPD plant
- Target production: 2029 or pilot-scale earlier
- Logrosán Tungsten Project (Spain):
- 5,400m drilling completed; all holes intersected economic mineralization
- Estimated 2.3M tons resource (growing)
- Zero royalty; corporate tax 25%
- Mozambique Lithium-Tantalum:
- 150 km² area; multiple pegmatite zones
- Planning 1,500-2,000m drilling
- Potential for 2028 commercialization; royalty <3%
Projects Under Due Diligence
- Finland Gold Project: 45 km²; 6 tons gold + 9 tons silver resource
- Brownfield Gold Project: 3.3 tons gold resource, potential to 10+ tons
- Graphite Project: 1km explored, 10km potential; 94% recovery; flaky graphite for batteries
Financial Performance
- Q2 FY27 PAT: ₹13.91 Cr (vs ~₹6 Cr previous quarter)
- H1 FY27 Consolidated Loss: ₹9.28 Cr (despite associate profits)
- Consolidated Loss Reason: Tier 2 projects and subsidiaries not yet in production
Key Dates & Regulatory References
- Earnings Call Date: November 20, 2026
- Kyrgyzstan Commissioning: September 12, 2026
- Ganajur Supreme Court Hearing: December 1, 2026
- Fundraising Approval: August 2026 (Board), September 2026 (EGM)
- SEBI Regulation: Reg. 30 disclosure
Management Commentary & Guidance
- Swarnagiri: Expect 450-500 kg production in FY27; inventory built for festive season sales
- Kyrgyzstan: Winter operations ongoing; production clarity expected in 15-20 days
- Funding Strategy: Future funding through market instruments (debt/equity) or offtake arrangements for critical minerals
- Promoter Stake: Exploring increase in promoter stake and Kyrgyzstan project stake
- Gold Price Impact: Current price decline may reduce EBITDA margins from 70% to 65-67%
- Critical Minerals Contribution: Expected to remain secondary to gold (60% revenue from gold) in medium term
Parties Involved
- Subsidiaries/Associates: Thriveni Lloyds Swarnagiri, Avelum Partners
- Partners: Hira Group (26% in Avelum), Medetbek (14% in Avelum), Kyrgyzaltyn (govt partner)
- Legal Counsel: Engaged senior counsel for Supreme Court case
- Regulators: SEBI, BSE, Supreme Court of India, Ministry of Mines
Capital Structure Impact
- No immediate dilution planned; considering offtake arrangements instead of equity dilution for critical minerals
- Exploring stake increase in Kyrgyzstan project
Cash Flow Implications
- ₹137 Cr fundraising for exploration
- Swarnagiri profits not yet distributed as dividends
- Future capex requirements: ₹400-600 Cr for critical mineral projects
Forward-Looking Statements (Explicitly Disclosed)
- Kyrgyzstan production targets: 180 kg (FY27), 300 kg (FY28), 700-750 kg (underground)
- Project commercialization: Mozambique (2028), Bhalukona (2029), others (2029-2030)
- Ganajur timeline: 2-3 years to production if approved
- Planned analyst meets before December 15, 2026