GUJARAT INDUSTRIES POWER COMPANY LTD.

Management Participants

  • Mr. K.K. Bhatt - Executive Director (Finance) and Chief Financial Officer
  • Mr. Shalin Patel - Company Secretary and Compliance Officer

Key Operational and Financial Highlights

1. 600 MW Khavda Solar Plant (Operational):

  • The plant was fully allocated in November 2025 and is evacuating power at full capacity.
  • Current Capacity Utilization Factor (CUF) is 33.24%.
  • The plant operates under a Power Purchase Agreement (PPA) with GUVNL at a tariff of ₹2.73 per unit.
  • For FY 2026-27, management expects revenue of approximately ₹420 crores and EBITDA of approximately ₹350-360 crores from this asset.
  • The plant has a one-year debt moratorium that ended in June 2026; loan repayments are scheduled to begin in the next quarter (Q2 FY27).

2. 500 MW Khavda Solar Plant (Under Development):

  • The project is at a very advanced stage of commissioning.
  • Phased commissioning is anticipated post-monsoon, starting with 200 MW, followed by another 200 MW and finally 100 MW over the subsequent couple of months.
  • Full commissioning is expected by the end of Calendar Year 2026.
  • The delay is attributed to power evacuation infrastructure not being fully ready by CTUIL.
  • Upon full commissioning, this project is expected to add approximately ₹450 crores to the company's peak debt, taking total debt to around ₹4,500 crores.
  • The revenue model is similar to the 600 MW plant at ₹2.73/unit.

3. Existing Thermal Power Plants (SLPP 1 & 2):

  • Both lignite-based thermal plants are operating with a strong Plant Load Factor (PLF), exceeding threshold limits of 75% and 80% respectively.
  • There are no issues with power evacuation for these plants.
  • Revenue from these plants for FY 2025-26 was approximately ₹1,103 crores.
  • These plants are now debt-free.

4. Other Renewable Assets:

  • FY 2025-26 revenue breakdown for other RE assets: Solar (ex-Khavda): ₹152 crores, Wind: ₹86 crores, 75 MW Solar: ₹38 crores.
  • These existing RE assets are also largely debt-free.

5. Financial Projections and Debt:

  • Long-term borrowing stood at ₹3,247 crores as of 31st March 2026.
  • Peak debt is projected to be around ₹4,500 crores after the commissioning of the 500 MW solar project.
  • The average coupon rate on borrowings is 7.8% (floating).
  • For FY27, projected interest cost is ₹250-260 crores and depreciation is ₹425-450 crores.
  • Once the 500 MW plant is fully operational for a full year, management anticipates a consolidated EBITDA in the range of ₹950-1,000 crores.

6. Capacity Expansion - 750 MW Thermal Plant:

  • GUVNL has given in-principle approval for a new 3x250 MW lignite-based thermal power station on a cost-plus basis under Section 62.
  • Tenders have been floated, with BHEL among the observed parties.
  • The project capex is estimated at ~₹6,000 crores, with an anticipated debt-equity ratio of 80:20.
  • The project has a gestation period of 3-4 years, with commissioning targeted for 2032-33.
  • Lignite supply for the expansion is secured from available reserves in the region.

7. Baroda Gas-Based Power Plant:

  • The 310 MW gas-based plant remains idle due to the geopolitical situation affecting gas availability.
  • Management is repurposing the site for Battery Energy Storage Systems (BESS).
  • GUVNL has approved a 20/120 MW BESS project at this location, and tenders are already in place.
  • Plans are underway for an additional 30/160 MW BESS in the coming year.
  • The existing switchyard and evacuation infrastructure will be utilized for the BESS projects.
  • The pilot BESS project is expected to generate revenue at ~₹6 per unit and take about one year to become fully operational.

8. Solar Park Development:

  • GIPCL has been allotted a 2,375 MW solar park at Khavda.
  • The company is developing 1,100 MW on its own (600MW + 500MW).
  • The remaining capacity has been allocated to third parties like Coal India, SJVN, and SAEL, who have direct PPAs with GUVNL.
  • As the park developer, GIPCL will provide evacuation and infrastructure, generating O&M revenue.
  • Net revenue from park development is expected to be ~₹20-25 crores annually for 25 years.
  • Through land optimization, an additional 200 MW solar capacity is planned at the Khavda location, requiring a capex of ₹800-1,000 crores.

9. Dividend Policy:

  • Management expressed a commitment to continue paying dividends, acknowledging obligations to investors. The specific amount will be determined based on post-commissioning figures of the 500 MW project.