Financial Performance Highlights

H1 FY27 Consolidated Results:

  • Total Income: ₹209 crores
  • EBITDA: ₹27 crores
  • EBITDA Margin: 13%
  • Net Profit: ₹11 crores
  • Net Profit Margin: 5%

Q2 FY27 Consolidated Results:

  • Total Income: ₹116 crores
  • EBITDA: ₹12 crores
  • EBITDA Margin: 10%
  • Net Profit: ₹3.9 crores

Order Book Analysis

The company reported a current order book of ₹600 crores with the following segmentation:

  • Educational Institutes: ₹115 crores (20%)
  • Housing: ₹250 crores (40%)
  • Sports Infrastructure: ₹183 crores (30%)
  • Transport & Logistics: ₹45 crores
  • Commercial Office: Remaining portion

Project Updates

IIT Delhi Project (₹98.85 crores):

  • Project has commenced with two billings completed
  • Total billed amount: ₹4 crores to date
  • Target billing until March 2027: ₹25 crores
  • Specialized steel purchase orders already placed

Central University of Punjab, Bathinda (₹172.92 crores):

  • One building handed over 6 months ahead of schedule
  • Second building to be handed over 5 months ahead of schedule
  • ₹126 crores already achieved out of ₹172 crores
  • Project expected to complete before March 2027

Bidding Pipeline and Growth Strategy

Management identified three active tenders in the bidding pipeline with values ranging from ₹200-300 crores each:

  • Sports infrastructure project
  • General infrastructure project
  • Institutional college project

Target to add ₹500-600 crores in new projects by March 2027. The company is expanding geographically with new bids in Madhya Pradesh and focusing on specialized projects with less competition and better profitability.

Prequalification Status

The company is currently classified as a Class 1 Super Contractor with bidding capacity up to ₹650 crores. Management expects to qualify for ₹800-1,000 crore projects within 1-2 years after completing three projects of ₹300-400 crore value (one already completed).

Margin Pressures and Market Conditions

Q2 profitability was affected by volatile material prices:

  • Steel prices increased from ₹48-49/kg to ₹67/kg
  • Copper, aluminum, and transportation costs also increased
  • Although projects have escalation clauses, there's a 3-month lag in price variation recovery
  • Company has been cautious in bidding over last 5-6 months due to market volatility

Working Capital and Cash Flow

H1 FY27 Standalone Cash Flow:

  • Operating profit before working capital changes: Positive ₹27 crores
  • Net cash from operating activities: Negative ₹11.97 crores
  • Primary reason: Increase in trade receivables due to longer billing cycles in new projects (NBCC, Haryana Cricket Association Stadium, Unitech projects)
  • These projects have 7.5% retention money and 40+ day payment terms

Inventory Management:

  • Standalone inventory stood at ₹176.26 crores as of September 2026
  • Increase due to proactive procurement to hedge against volatile prices

Guidance and Outlook

Revenue Growth: 10-15% year-on-year growth targeted for FY27 and FY28

Margin Target: Maintain current margin levels despite market volatility

Order Book Visibility: Current order book provides 1.5 years of revenue visibility

Operational Challenges

  • Pollution-related construction bans in NCR region affecting Q3 operations (particularly KG Marg MEA project and IIT Delhi project)
  • Labor shortages across industry prompting increased mechanization
  • Extended billing cycles in new projects impacting working capital requirements

Contract Structure

  • Approximately ₹200 crores of order book comprises fixed-price contracts
  • Majority of projects have price escalation clauses linked to Wholesale Price Index
  • In some fixed-price contracts (e.g., Haryana Cricket Association), steel is provided free of cost by client