Financial Performance Q2 & H1 FY27

Garden Reach Shipbuilders & Engineers Limited held its Q2 & H1 FY27 earnings conference call on November 19, 2026. The company reported strong financial performance:

Q2 FY27 Results (YoY Comparison):

  • Revenue from operations increased from ₹1,677 crores to ₹1,827 crores, representing 9% growth
  • Profit after tax increased from ₹154 crores to ₹172 crores, representing 12% growth

H1 FY27 Results (YoY Comparison):

  • Revenue from operations increased from ₹2,987 crores to ₹3,641 crores
  • Profit after tax increased from ₹274 crores to ₹345 crores, representing 26% growth

Operational Highlights and New Order Wins

Since the last investors call, GRSE secured four significant shipbuilding orders:

1. Four Platform Supply Vessels (PSVs) from Oil and Natural Gas Commission (ONGC)

2. One 15-tonne bollard pull battery propulsion tug from Syama Prasad Mookerjee Port

3. 200 passenger electric ferries from West Bengal tourism department

4. Next Generation Corvettes (NGC) contract signed on November 2, 2026, with order value of over ₹32,000 crores

Order Book Position

As of September 30, 2026, the order book stood at ₹12,977.93 crores. With the NGC contract, the current order book value reached approximately ₹44,846 crores.

Order Book Composition:

  • Shipbuilding contributes 96% of orders
  • Defence segment: 70%
  • Non-defence segment: 29%
  • 13 projects comprising 50 platforms

Project Breakdown:

  • Four naval projects: P-17 Alpha, Anti-Submarine Shallow Water Craft, Next Generation Offshore Patrol Vessel, Next Generation Corvette
  • Two export projects: 12 Multipurpose vessels for German client, 1000 cubic meter Trailing hopper suction dredger for Bangladesh
  • Three research vessel projects: Ocean Research Vessel, two Coastal Research Vessels, Acoustic Research ship
  • Two Hybrid Ferry projects: 13 ferries for West Bengal government
  • One fully electric Tug for Syama Prasad Mookerjee Port
  • Four Platform Supply Vessels for ONGC

Project Execution Status and Timelines

P-17 Alpha Project: Three-ship project with two vessels delivered ahead of schedule. Third vessel completed trials, ready for delivery in November 2026.

Anti-Submarine Shallow Water Craft: Eight-ship project with five vessels delivered (latest on November 5, 2026). Remaining status:

  • Sixth vessel: 99% complete, delivery expected next week
  • Seventh vessel: 75% complete
  • Eighth vessel: 63% complete

Project completion expected first half of calendar year 2027.

Next Generation Offshore Patrol Vessel: Four-ship project with three vessels launched. Fourth vessel launch planned early 2027 (Q4 FY27).

Next Generation Corvette: Pre-production activities (design and procurement) commenced. Nine-year project with first vessel delivery expected latter half of calendar year 2032, final vessel by 2035-2036.

Other Projects:

  • Ocean Research Vessel: 55% complete, delivery planned end 2027
  • Acoustic Research Ship: 40% complete, delivery planned first half 2028
  • Coastal Research Vessel: Keel laying completed, delivery expected FY29
  • Ferry Project (Transport Dept): Two vessels at 90% completion, delivery within a month. Project completion first half 2027
  • Bangladesh Dredger: Launched, final outfitting in progress, delivery expected April 2027

Future Order Pipeline

RFPs with Bids Submitted (₹25,000 crores):

  • 22 interceptor boats for Indian Coast Guard (₹1,000-1,100 crores)
  • 31 water jet FACs for Indian Navy (₹15,000 crores, split L1:19 vessels, L2:12 vessels)
  • 120 Fast Interceptor Crafts for Indian Navy (₹4,500-5,000 crores)
  • 6 Next Generation Offshore Patrol Vessels for Indian Coast Guard (₹3,500 crores)

Live RFPs (₹1,47,000 crores):

  • P-17 Bravo Project: 7 platforms, AoN value ₹70,000 crores (L1:4 ships, L2:3 ships)
  • Landing Platform Dock Project: AoN value ₹33,000 crores
  • Mine Countermeasure Vessel Project: AoN value ₹44,000 crores

Management expects order clarity by end of FY27, with P-17 Bravo L1 declaration expected in current financial year and contract conclusion by Q4 FY28.

Capacity Expansion Plans

Current Capacity: Concurrent construction of 28 platforms, expanding to 32 platforms by December 2026.

Expansion Projects:

1. Timber Pond Facility: ₹100 crores investment, 130-meter dry dock, 120-meter slipway

2. Howrah Facility: ₹70 crores investment for medium/small vessels (tugs, ferries)

3. Raichak Facility: ₹2,900 crores investment, 200-meter dry dock, capable of 60,000 DWT commercial ships

4. West Coast Expansion: DPR and partnership activities in progress

Major projects (Raichak and west coast) expected completion in 3.5-4 years. Expansion supported by Government of India's ₹69,000 crore Shipbuilding Revitalization Plan.

Revenue Recognition and Project Phasing

For NGC project, revenue recognition expected to commence from FY28 at approximately 7.5-8% of project cost during pre-production phase. Peak revenue recognition typically occurs at 40-65% physical progress.

Management indicated FY26 and FY27 as peak years, with expected trough in FY29 before NGC revenue contribution becomes substantial. Base and depot spares (approximately 15% of project value) typically delivered within one year after project completion.

Margin Profile and Competition

NGC margins described as "adequate and akin to Anti-Submarine Shallow Water Craft project." Company has been operating in competitive bidding environment for six years.

Indigenous Content

Warship projects achieve 85% indigenous content. Commercial export ships achieve 40-45% indigenous content due to client specifications. Domestic commercial ships achieve 60-65% indigenous content.

MSME Engagement

70% of procurement from MSMEs. Company implementing long-term rate contracts (3-5 years) and demand aggregation to provide visibility and support working capital needs.

Robotics and Technology Adoption

Company has implemented Robotics in manufacturing processes, including collaborative robots (Cobots) for shipbuilding applications. Usage expanded to bailey bridge fabrication and shipbuilding operations.

Commercial Shipbuilding Opportunities

Government has aggregated demand for 437 vessels. Immediate opportunities include container ships and additional platform supply vessels. Company recently won first order through segregation initiative (ONGC PSVs).