Key Performance Highlights - Q2 FY27
Financial Performance
Standalone Results:
- Turnover: ₹895.8 crore (down 6.5% YoY from ₹957.8 crore in Q2 FY26)
- Net Profit: ₹36.8 crore (up 0.3% YoY from ₹36.7 crore)
- EBITDA: ₹109.2 crore (down 29.2% YoY from ₹154.2 crore)
- EBITDA Margin: 12.2% (vs 16.1% in Q2 FY26)
- Finance Cost: ₹82.6 crore (down 26.4% YoY from ₹112.2 crore)
- Tax Expense: ₹11.8 crore (down 36.0% YoY from ₹18.4 crore)
Consolidated Results:
- Revenue: ₹896.8 crore (down 6.7% YoY from ₹960.7 crore)
- Profit: ₹22.6 crore (down 52.8% YoY from ₹47.8 crore)
- EBITDA: ₹102.8 crore (down 30.4% YoY from ₹147.8 crore)
- EBITDA Margin: 11.5% (vs 15.4% in Q2 FY26)
Order Book & Business Development
- New order secured: ₹524 crore
- L1 bids: ₹2,010 crore (HCC share: ₹1,557 crore)
- Bids submitted: 16 bids worth ₹34,805 crore under evaluation (HCC share: ₹32,386 crore)
- Pipeline under pursuit: ₹85,907 crore
- Order Backlog: ₹12,901 crore
Debt Reduction
- Prepaid ₹100 crore of debt in Q2 FY27
- Additional ₹108 crore debt prepayment targeted by December 2026
Legal Development
- Supreme Court upheld ₹210 crore arbitration award in favor of HCC
- Monies expected to be released in Q3 FY27
Operational Highlights
Project Awards & Recognition:
- Mumbai Coastal Road Project (Package II) won Best Project award in Bridge/Tunnel category at 2026 ENR Global Best Projects awards
Operations Updates for Major Projects:
1. Indore Metro: TBM 1 & 2 lowering completed, TBM mining commenced from Airport Station, excavation progressing across five stations
2. Patna Metro PC 05 & PC 06: Factory Acceptance Test completed, casting yard development underway
3. Agardanda Creek Bridge: Work progressed on foundations and bridge segments construction
4. Bhivpuri PSP (3x333.33 MW): Excavation progressing across multiple components including Lower Reservoir and Powerhouse
5. Vishnugad Pipalkoti HEP (4x111 MW): 79% of concrete works completed at dam and intake structures
6. Tapovan Vishnugad HEP (4x130 MW): Excavation progressing across all faces with varying completion percentages
7. Fast Reactor Fuel Cycle Facility (FRFCF): Cell slab works completed in Blocks 3 and 4
8. Hindalco PS & PSS: Pot Superstructure prototype approved; 23 of 181 pot shells fabricated
9. Parwan Dam: Initial filling of dam reservoir completed
10. Salal Dam: Three dredgers mobilised, tested and commissioned
Company Background
- Nation building since 1926
- Contributed to 60% of India's installed nuclear power capacity
- Contributed to 26% of India's installed hydro power capacity