Company Disclosure
Operational & Order Book Highlights
Order Book Composition (as of September 2026)
Total Order Book: ₹136,849 million
Sector-wise Breakdown:
- Road: ₹87,921 million (64%)
- Railway: ₹28,833 million (21%)
- Transmission: ₹14,001 million (10%)
- BESS: ₹5,026 million (4%)
- Solar: ₹1,068 million (1%)
Project Type Breakdown:
- EPC: ₹95,234 million (70%)
- HAM-Road: ₹41,615 million (30%)
Client Type Breakdown:
- Government: ₹88,440 million (65%)
- Private: ₹48,409 million (35%)
Geographical Distribution
36 projects across 14 states:
- Maharashtra: 35.1% share
- Jharkhand: 19.6% share
- Odisha: 12.4% share
- Uttar Pradesh: 10.2% share
- Gujarat: 6.6% share
- Delhi: 5.5% share
- Other states: 11.6% share
Significant Events and Project Updates (Till September 2026)
L1 Status Declared
1. Mirzapur Thermal Energy, UP (Railway) - LOA Date: April 14, 2026
2. Welspun Enterprises Ltd (Road - Pune-Shirur) - LOA Date: May 11, 2026
3. REC Power Development (Transmission - WR-ER Part-C) - LOA Date: June 12, 2026
4. REC Power Development (Transmission - Ranipur-Chunar) - LOA Date: August 18, 2026
5. Govt of Rajasthan (L&D - ITI Upgradation Bhiwadi Cluster) - LOA Date: August 14, 2026
Appointed Date Declaration
- Jharkhand Package-10 HAM Project: Construction of 6-lane Greenfield Varanasi Ranchi Kolkata Highway - Appointed Date: May 30, 2026
Contract Agreements Signed
1. OD-3 (CRRR) Govindpur-Tangi: April 24, 2026
2. WR-ER Part-C (T&D): June 30, 2026
3. Ranipur-Chunar (T&D): September 26, 2026
4. ITI Upgradation Bhiwadi Cluster (L&D): September 07, 2026
Completion Certificates
- UER-2, Delhi: Development of 6-lane Urban Extension Road - Completion certificate effective February 28, 2025 (Letter no. 1536 dated September 23, 2026)
- Ganga Expressway, UP: Provisional Completion Certificate effective April 30, 2026 (Letter no. ARTL/1909 dated May 30, 2026)
HAM Projects Update
Equity and Debt Deployment (All figures in ₹ Million)
| Project | State | BPC | Grant Amount | Invested Equity | Total Sanctioned Debt | Debt as of Sept 2026 |
| Raipur Visakhapatnam AP-1* | Andhra Pradesh | 10,601 | 4,240 | 1,687 | 4,379 | 4,153 |
| Karnal Ringroad | Haryana | 9,971 | 3,988 | 1,574 | 4,650 | 4,481 |
| Varanasi Kolkata Pkg-10 | Jharkhand | 13,031 | 5,212 | 807 | 6,200 | 1,541 |
| Varanasi Kolkata Pkg-13 | Jharkhand | 9,251 | 3,700 | 718 | 4,470 | 1,355 |
| Chennai Tirupati II** | Andhra Pradesh | 8,167 | 3,267 | 1,154 | 4,043 | 2,100 |
| 84 Kosi Parikrama | Uttar Pradesh | 7,631 | 3,052 | 714 | 3,900 | 963 |
| Narol Sarkhej | Gujarat | 7,811 | 3,124 | 1,027 | 4,050 | 1,611 |
| Gobindpur Tangi | Odisha | 15,821 | 6,328 | 25 | 8,200 | - |
| Total | | | | 7,706 | 39,892 | 16,204 |
*BPC including GST
**After BPC descope of ₹454.3 million and Debt reduction of ₹306.8 million
Financial Performance
Standalone Results (₹ Million)
| Particulars | Q2 FY27 | Q2 FY26 | YoY Change | H1 FY27 | H1 FY26 | YoY Change |
| Revenue from Operations | 8,832.19 | 11,537.47 | -23.4% | 17,904.55 | 28,629.90 | -37.5% |
| EBITDA | 1,047.26 | 1,465.65 | -28.5% | 1,817.42 | 3,822.32 | -52.5% |
| EBITDA Margin % | 11.9% | 12.7% | | 10.2% | 13.4% | |
| PAT | 321.31 | 673.06 | -52.3% | 604.03 | 1,927.75 | -68.7% |
| PAT Margin % | 3.6% | 5.8% | | 3.4% | 6.7% | |
| Exceptional Item | -21.23 | - | | 279.89 | - | |
Consolidated Results (₹ Million)
| Particulars | Q2 FY27 | Q2 FY26 | YoY Change | H1 FY27 | H1 FY26 | YoY Change |
| Revenue from Operations | 9,735.87 | 9,045.03 | +7.6% | 20,741.72 | 23,867.05 | -13.1% |
| EBITDA | 2,495.26 | 2,062.33 | +21.0% | 5,533.28 | 4,658.73 | +18.8% |
| EBITDA Margin % | 25.6% | 22.8% | | 26.7% | 19.5% | |
| PAT | 797.62 | 518.36 | +53.9% | 352.44 | 1,511.00 | -76.7% |
| PAT Margin % | 8.2% | 5.7% | | 1.7% | 6.3% | |
| Exceptional Item | - | - | | -1,467.81 | - | |
Debt Position
Consolidated Debt Break-up (₹ Million)
| Particulars | September 2026 | March 2026 |
| Standalone Debt | 15,952 | 16,274 |
| Project Debts | 32,856 | 33,065 |
| Total Consolidated Debt | 48,808 | 49,339 |
| Consolidated Cash & Bank | 2,690 | 2,535 |
Standalone Debt Break-up (₹ Million)
| Particulars | September 2026 | March 2026 |
| Term Loan + Current Maturities | 4,817 | 4,964 |
| Non-convertible Debentures (NCD) | 4,000 | 4,000 |
| Working Capital | 7,135 | 7,310 |
| Total Standalone Debt | 15,952 | 16,274 |
| Standalone Cash & Bank | 1,632 | 1,287 |
Company Contacts
- CFO: Vikas Jain (vikas.jain@hginfra.com)
- Investor Relations: Go India Advisors - Saloni Ajmera (+91 9930577801), Selina Sheikh (+91 918433818768)