• Event Type: The document is a transcript of the Q2 and H1 FY2026-27 Earnings Conference Call, which included a presentation by management followed by a Q&A session with analysts and investors.
  • Date and Time: The earnings call was held on November 06, 2026. A specific start time was not mentioned in the transcript.
  • Purpose: The stated purpose of the call was to discuss the company's financial results for the second quarter and half year ended September 30, 2026, and to provide a comprehensive operational update on all of its assets.
  • Earnings Timing: The company aligned the results announcement and the earnings call on the same day this quarter, a departure from its usual practice, due to the Diwali holiday period.
  • Management Participants: The call was led by Mr. Baroruchi Mishra, Managing Director and Chief Executive Officer and Mr. Debabrata Das, Chief Financial Officer.
  • Availability of Materials: The transcript of the earnings call was attached to the regulatory filing and is also available on the company's website at https://hoec.com/earnings-call/.
  • UPSI Statement: The transcript itself does not contain a specific compliance statement regarding Unpublished Price Sensitive Information (UPSI). The content is a record of the discussion that took place during the publicly held call.

Operational and Financial Highlights (as disclosed)

  • Financial Period Discussed: Q2 (July-Sept) and H1 (Apr-Sept) of FY 2026-27.
  • Q2 FY27 Financials: Consolidated revenue stood at ₹151.78 crores. EBITDA was ₹37.51 crores (24.71% margin). Profit After Tax (PAT) was ₹19.03 crores.
  • H1 FY27 Financials: Revenue was ₹275.78 crores. EBITDA was ₹63.18 crores. PAT was ₹25.10 crores.
  • Key Financial Drivers: The improvement in profitability was driven by an increase in gas sales and the realization of ₹80 crores from the sale of crude oil inventory that was previously disputed with HPCL. Approximately 36,103.90 metric tons of this inventory remains to be sold.
  • Liquidity & Debt: The company closed September 2026 with cash and cash equivalents of ₹166 crores and gross debt of ₹211.11 crores, resulting in net debt of ₹44.90 crores. Net debt to EBITDA stood at 0.71x. The company raised ₹179 crores in H1, including a ₹125 crore credit facility for funding B-80 workover capex.
  • Production Guidance: Management reiterated its operational targets:
  • Mid-2027: Target of 10,000 barrels of oil equivalent per day (net to HOEC).
  • FY28: Target of 22,000 BOE per day.
  • FY29: Target of 30,000-32,000 BOE per day.
  • Reserves Update: With the award of the B-174 field, the company's 2P (Proved + Probable) reserves have crossed 100 million barrels of oil equivalent (MMBOE), reaching approximately 104 MMBOE.
  • Asset-wise Operational Updates:
  • B-80 (Offshore Mumbai): Workovers on the D1 and D2 wells are planned for end-Nov/early-Dec 2026, targeting an additional 1,000-1,500 BOPD and 5-7 MMSCFD of gas. Contracts are awarded, with a rig expected by late November. Drilling of three new wells is planned thereafter.
  • Assam (Dirok): Current gross production is ~0.7 million SCM. Field potential is 1.2 million SCM, ramping to 2 million SCM with new wells. The increase is contingent on the debottlenecking of the DNPL pipeline, which is expected by December 2026.
  • PY-1 (Cauvery Offshore): Well intervention (coil tubing) is planned to increase production. Drilling of two new wells is planned for mid-2027 but is contingent on securing a firm take-or-pay gas sales agreement with IOCL or GAIL.
  • Kharsang (Assam): Plans to drill nine more wells, aiming to double oil production from ~700 BOPD to 1,200-1,400 BOPD. Drilling is expected to start in Jan/Feb 2027.
  • B-174 (Offshore Mumbai): Awarded DSF block with DGH-quoted 2P reserves of 21 MMBOE. Development planning is underway.

Additional Notes Section

  • The document is an enclosed transcript of the earnings call, filed pursuant to Regulation 30 of the SEBI (LODR) Regulations, 2015.
  • The transcript contains extensive forward-looking statements regarding operational plans, production targets, and project timelines.
  • Tagging: