Date: 30th October 2026
Financial Results (Standalone)
Q2 FY 2026-27 Financial Highlights (₹ crore):
- Turnover: ₹2,15,000
- Net Profit: ₹6,703
- EPS: ₹4.84
Half Year FY 2026-27 Financial Highlights (₹ crore):
- Turnover: ₹4,43,000
- Net Profit: ₹14,473
- EPS: ₹10.45
Operational Highlights
Refinery Operations Q2 FY26-27:
- Throughput: 18.1 MMT
- Capacity utilization: 102.3%
- Distillate Yield: 78.9%
- Fuel & Loss: 8.5%
- Utilization of High Sulphur crude: 54.6%
Pipeline Operations Q2 FY26-27:
- Throughput: 25.3 MMT
- Capacity utilization: 64.3%
Marketing Operations Q2 FY26-27 (Sales in MMT):
Petroleum Products - Inland Sales: 21.140
- HSD: 8.996
- MS: 4.424
- LPG: 3.470
- ATF: 1.168
- FO/LSHS: 1.002
- Lubes & Greases: 0.261
- Others: 1.819
Petroleum Products - Exports: 1.227
Sub-Total Petroleum Products: 22.367
Other Products:
- Gas: 1.933
- Petrochemicals Domestic: 0.834
- Petrochemicals Exports: 0.024
- Others: 0.070
Sub-Total Other Products: 2.861
Total Sales: 25.228 MMT
Capex & Major Projects Update as on 30.09.2026
Major Projects Status:
- Project 1: Gross Approved Cost ₹38,231 crore, Physical Progress 95.0%, Expected Completion Dec'26
- Project 2: Gross Approved Cost ₹18,936 crore, Physical Progress 90.1%, Expected Completion Dec'26
- Project 3: Gross Approved Cost ₹18,113 crore, Physical Progress 92.5%, Expected Completion Dec'26
- Project 4: Gross Approved Cost ₹13,805 crore, Under Commissioning (Mechanically completed in Sep'26)
- Project 5: Gross Approved Cost ₹9,028 crore, Under Commissioning (Mechanically completed in Jul'26)
- Project 6: Gross Approved Cost ₹3,220 crore, Physical Progress 65.6%, Expected Completion Jul'27
- Project 7: Gross Approved Cost ₹2,949 crore, Physical Progress 92.2%, Expected Completion Dec'26
Segment-wise Capex incurred during H1 FY 26-27 (Provisional, ₹ crore):
- Total: 32,700
- Refinery: 6,083
- Marketing: 3,396
- Petchem: 1,306
- Pipelines: 582
- Gas: 133
- R&D: 109
- E&P: 121
- Others: 432
Disclosure Context
This is a revised submission of the investor handout for unaudited financial results for Q2 and H1 FY26-27, replacing an incorrect file submitted earlier on 30th October 2026 at 06:51 PM. The company requested that the previously submitted file be ignored.