Key Operational Highlights
Capacity Addition:
- Added 873 MW during Q1 FY27, representing one of the largest single-quarter capacity additions in company history
- Cumulative additions reached approximately 1.1 GW till date (since April 2026)
- 150 MW from early commissioning of Tidong Hydro (originally scheduled for October 2026), contributing incremental ₹20-22 crore to EBITDA in Q1
- Added 225 MW organic renewable energy capacity in July till date
- Total installed capacity now stands at 14.6 GW, with renewables constituting 61% (8.9 GW) and thermal at 5.7 GW
FY27 Targets:
- On track to deliver 3 GW capacity addition target for FY27
- ₹20,000 crore capex plan for FY27
- Achieved 36% of FY27 capacity guidance already
- Surpassed 87% of total capacity added in all of FY26
Financial Performance
Q1 FY27 Financials:
- Revenue: ₹5,437 crore (flat YoY)
- EBITDA: ₹3,103 crore (up 2% YoY)
- Depreciation: ₹890 crore (up 20% YoY)
- Interest costs: ₹1,519 crore (up 16% YoY)
- Profit After Tax: ₹533 crore (declined YoY)
- PAT attributable to shareholders: ₹471 crore
Balance Sheet & Liquidity:
- Successful ₹10,150 crore capital raise comprising:
- ₹3,000 crore preferential allotment to promoters (₹1,125 crore received, balance before June 2027)
- ₹3,150 crore from monetizing 2.5 crore shares of JSW Steel out of 7 crore shareholding
- ₹4,000 crore QIP anchored by marquee global and domestic institutional investors
- Cash and cash equivalents: ₹12,880 crore
- Net Debt to TTM EBITDA: 4.95x (improved from 5.2x in FY26)
- Target to maintain net leverage below 5x by 2030
- Cash return on net worth: ~14% (after adjusting for JSW Steel shareholding)
Operational Performance
Generation Metrics:
- Net generation: 12.9 billion units (down 5% YoY)
- Hydro generation: declined 26% YoY due to weak hydrology across basins
- Thermal generation: 8 billion units (down 6% YoY)
- Solar generation: up 29% YoY
- Wind generation: up 3% YoY
- Mahanadi generation impacted by 17-day evacuation availability issue (184 MU loss, categorized under Force Majeure)
Environmental Impact:
- Avoided approximately 16-17 million tonnes of CO₂ emissions in FY26
- Avoided approximately 4.5 million tonnes of CO₂ emissions in Q1 FY27
Sector Overview
Power Demand Trends:
- Q1 FY27 demand grew 8.5% YoY (vs 0.9% growth in FY26)
- July month-till-date demand growth robust at ~12%
- Peak power demand touched 271 GW in May (surpassing FY26 peak of 245 GW)
- Expected to touch 300 GW in near term
- Merchant market DAM prices averaged ₹5.10/unit in Q1 FY27 (vs ₹4.40/unit in Q1 FY26, 16% increase)
Strategic Initiatives
Thermal Expansion:
- Signed definitive agreement to acquire Maruti Clean Coal & Power Limited (300 MW thermal plant in Chhattisgarh)
- 195 MW (net) long-term PPA with Rajasthan discoms (14 years residual life)
- 5% power at variable cost to Chhattisgarh discom
- ~64 MW merchant capacity
- Long-term FSA with SECL under SHAKTI scheme
- Salboni Phase 1: Received all key clearances, 100% land acquired, equipment orders placed, site work in progress
- KSK brownfield expansion: Land, water, rail, transmission infrastructure, and environmental clearances in place
Vertical Integration:
- Increased stake in Toshiba JSW Power Systems JV to 10.7% from 2.4%
- Ongoing acquisition of GE's boiler business expected to complete this quarter
- Commissioned wind blade manufacturing facility at Halol, Gujarat (450 blades/year capacity, supporting 600 MW wind installations annually)
- Second facility at Chitradurga expected by FY27
Energy Storage Business:
- 5 GWh battery plant commissioned in Q4 FY26
- Received first large external order worth ₹440 crore
Pumped Storage Projects:
- Bhavali project (1,500 MW) with MSEDCL: Environmental clearance received, land acquisition mostly complete, forest Stage 1 clearance received, orders placed to L&T (civil) and Voith (electromechanical)
- Kandhaura project (1,680 MW) with UP: ESC recommendation for EC received, forest clearance application submitted
- Expected high-teen IRRs for pumped storage projects
Connectivity Status
- 300 MW currently under TGNA facing curtailment (expected conversion to GNA by 31st August)
- 400 MW O2 Power project in Rajasthan under TGNA (connectivity expected September-October)
- 530 MW of remaining 1.9 GW FY27 capacity is group captive (off-grid, insulated)
- Remainder secured with connectivity operational
Management Commentary Outlook
- Expect hydro plants to catch up and achieve design energy for full year
- Utkal plant expected to generate higher EBITDA due to stable operations and PPA with Karnataka and Assam
- Committed to Strategy 3.0 delivery within defined timelines
- Evaluating selective, value-accretive acquisition opportunities
- Exploring merchant battery storage opportunities