Key Operational Highlights

Capacity Addition:

  • Added 873 MW during Q1 FY27, representing one of the largest single-quarter capacity additions in company history
  • Cumulative additions reached approximately 1.1 GW till date (since April 2026)
  • 150 MW from early commissioning of Tidong Hydro (originally scheduled for October 2026), contributing incremental ₹20-22 crore to EBITDA in Q1
  • Added 225 MW organic renewable energy capacity in July till date
  • Total installed capacity now stands at 14.6 GW, with renewables constituting 61% (8.9 GW) and thermal at 5.7 GW

FY27 Targets:

  • On track to deliver 3 GW capacity addition target for FY27
  • ₹20,000 crore capex plan for FY27
  • Achieved 36% of FY27 capacity guidance already
  • Surpassed 87% of total capacity added in all of FY26

Financial Performance

Q1 FY27 Financials:

  • Revenue: ₹5,437 crore (flat YoY)
  • EBITDA: ₹3,103 crore (up 2% YoY)
  • Depreciation: ₹890 crore (up 20% YoY)
  • Interest costs: ₹1,519 crore (up 16% YoY)
  • Profit After Tax: ₹533 crore (declined YoY)
  • PAT attributable to shareholders: ₹471 crore

Balance Sheet & Liquidity:

  • Successful ₹10,150 crore capital raise comprising:
  • ₹3,000 crore preferential allotment to promoters (₹1,125 crore received, balance before June 2027)
  • ₹3,150 crore from monetizing 2.5 crore shares of JSW Steel out of 7 crore shareholding
  • ₹4,000 crore QIP anchored by marquee global and domestic institutional investors
  • Cash and cash equivalents: ₹12,880 crore
  • Net Debt to TTM EBITDA: 4.95x (improved from 5.2x in FY26)
  • Target to maintain net leverage below 5x by 2030
  • Cash return on net worth: ~14% (after adjusting for JSW Steel shareholding)

Operational Performance

Generation Metrics:

  • Net generation: 12.9 billion units (down 5% YoY)
  • Hydro generation: declined 26% YoY due to weak hydrology across basins
  • Thermal generation: 8 billion units (down 6% YoY)
  • Solar generation: up 29% YoY
  • Wind generation: up 3% YoY
  • Mahanadi generation impacted by 17-day evacuation availability issue (184 MU loss, categorized under Force Majeure)

Environmental Impact:

  • Avoided approximately 16-17 million tonnes of CO₂ emissions in FY26
  • Avoided approximately 4.5 million tonnes of CO₂ emissions in Q1 FY27

Sector Overview

Power Demand Trends:

  • Q1 FY27 demand grew 8.5% YoY (vs 0.9% growth in FY26)
  • July month-till-date demand growth robust at ~12%
  • Peak power demand touched 271 GW in May (surpassing FY26 peak of 245 GW)
  • Expected to touch 300 GW in near term
  • Merchant market DAM prices averaged ₹5.10/unit in Q1 FY27 (vs ₹4.40/unit in Q1 FY26, 16% increase)

Strategic Initiatives

Thermal Expansion:

  • Signed definitive agreement to acquire Maruti Clean Coal & Power Limited (300 MW thermal plant in Chhattisgarh)
  • 195 MW (net) long-term PPA with Rajasthan discoms (14 years residual life)
  • 5% power at variable cost to Chhattisgarh discom
  • ~64 MW merchant capacity
  • Long-term FSA with SECL under SHAKTI scheme
  • Salboni Phase 1: Received all key clearances, 100% land acquired, equipment orders placed, site work in progress
  • KSK brownfield expansion: Land, water, rail, transmission infrastructure, and environmental clearances in place

Vertical Integration:

  • Increased stake in Toshiba JSW Power Systems JV to 10.7% from 2.4%
  • Ongoing acquisition of GE's boiler business expected to complete this quarter
  • Commissioned wind blade manufacturing facility at Halol, Gujarat (450 blades/year capacity, supporting 600 MW wind installations annually)
  • Second facility at Chitradurga expected by FY27

Energy Storage Business:

  • 5 GWh battery plant commissioned in Q4 FY26
  • Received first large external order worth ₹440 crore

Pumped Storage Projects:

  • Bhavali project (1,500 MW) with MSEDCL: Environmental clearance received, land acquisition mostly complete, forest Stage 1 clearance received, orders placed to L&T (civil) and Voith (electromechanical)
  • Kandhaura project (1,680 MW) with UP: ESC recommendation for EC received, forest clearance application submitted
  • Expected high-teen IRRs for pumped storage projects

Connectivity Status

  • 300 MW currently under TGNA facing curtailment (expected conversion to GNA by 31st August)
  • 400 MW O2 Power project in Rajasthan under TGNA (connectivity expected September-October)
  • 530 MW of remaining 1.9 GW FY27 capacity is group captive (off-grid, insulated)
  • Remainder secured with connectivity operational

Management Commentary Outlook

  • Expect hydro plants to catch up and achieve design energy for full year
  • Utkal plant expected to generate higher EBITDA due to stable operations and PPA with Karnataka and Assam
  • Committed to Strategy 3.0 delivery within defined timelines
  • Evaluating selective, value-accretive acquisition opportunities
  • Exploring merchant battery storage opportunities