Webcast Information
The investor meet webcast is accessible at: https://digitalevents.in/events/login?eventId=SC7PMTQ
The presentation is also available on the company's website at: nbccindia.in/webEnglish/PresentationNTranscript
Business Overview
- 65+ years of experience (Incorporated in 1960)
- One of the Largest Construction Companies in India
- PAN India & Global Presence
- Business Segments: Project Management Consultancy (PMC), Engineering Procurement & Consultancy (EPC), Real Estate
- Business Model USP: PMC Model, Redevelopment Model
- Consolidated Order Book as on 31.03.2026: ₹1,27,820 Crore
Subsidiary Companies
- HSCC – 100% subsidiary
- HSCL – 51% subsidiary
- NSL – 100% subsidiary
- NBCC Overseas Real Estate LLC – 100% subsidiary
- DWC LLC – 100% subsidiary
Financial Performance
- FY 2025-26: Declared Final Dividend of ₹0.46 per share (₹1.0 per share full year)
- Q4 FY 2025-26: ₹6,175 Crore (Consolidated)
Order Book and Business Secured
Order Book as on 31.03.2026 (Consolidated): ₹1,27,820 Crore (excluding GST)
New Business Secured & Work Awarded as on 31.03.2026 (₹ in Crore):
- Business Secured in Q4 2025-26: ₹3,681 Crore + ₹69 Crore + ₹1,269 Crore + ₹167 Crore = ₹5,186 Crore
- Total Business Secured in FY 2025-26: ₹15,390 Crore + ₹229 Crore + ₹2,632 Crore + ₹529 Crore = ₹18,780 Crore
- Works Awarded to Contractors in Q4 2025-26: ₹5,778 Crore + ₹17 Crore + ₹285 Crore + ₹95 Crore = ₹6,175 Crore
- Works Awarded in FY 2025-26: ₹9,768 Crore + ₹549 Crore + ₹972 Crore + ₹257 Crore = ₹11,546 Crore
Major Projects Secured During Q4 FY26
- Rajasthan State Industrial Development & Investment Corporation (RIICO): Urban development and Innovation Projects - PMC (Redev) - ₹2,100.00 Crore
- Delhi Development Authority (DDA): DDA Staff Quarters at Old Rajinder Nagar & Safdarjung Development Area - PMC (Redev) - ₹775.27 Crore
- Department of Fisheries Uttarakhand: Construction of Proposed Namami Ganga Aquarium - ₹232.13 Crore
- Oil India Limited: Housing Complex at Duliajan, Assam - PMC - ₹227.99 Crore
- NLC India Limited: Rehabilitation and Resettlement colony - ₹90.23 Crore
- Neyveli Uttar Pradesh Power Limited (NUPPL): ₹88.18 Crore
- Odisha School Programme Authority: Implementation of Civil works - ₹83.76 Crore
- Ministry of Home Affairs: Bridges over River Hari and River Luva in Meghalaya - ₹76.27 Crore
- Dharanidhar University, Keonjhar, Odisha: Academic building and infrastructure - Value not specified
Major Projects Secured During FY26
- Work of Urban development and Innovation Projects RIICO: PMC/Redev. - ₹4,916 Crore
- Development of Naveen Nagpur: PMC/Redev. - ₹2,966 Crore (Nagpur Metropolitan Region Development Authority)
- Re-development of Tulsi Niketan at Ghaziabad: PMC/Redev. - ₹643 Crore (Ghaziabad Development Authority)
- Redevelopment of DDA Staff Quarters at Old Rajinder Nagar: PMC/Redev - ₹438 Crore
- Chandrapura Thermal Power Station: PMC - ₹498 Crore (Damodar Valley Corporation)
- African Zoo, Safari Plaza, Animal Hospital: PMC - ₹355 Crore (FDCM Gorewada Zoo Limited, Nagpur)
- Work at HVF and AVNL Estate: PMC - ₹350 Crore (Heavy Vehicles Factory)
- Central University of Kashmir: PMC - ₹340 Crore
- DDA Staff Quarters at Safdarjung Development Area: PMC/Redev. - ₹338 Crore
- Work of Indian Institute of Technology, Mandi: PMC - ₹333 Crore
- Meerut Development Authority (MDA): PMC/Redev - ₹297 Crore
Major Projects Awarded During FY26
- Redevelopment of GPRA Colony at Sarojini Nagar - Construction of Type-V Quarters (800 Nos): ₹900 Crore
- Redevelopment of GPRA Colony at Sarojini Nagar - Construction of Residential Apartments (500 Nos): ₹887 Crore
- Redevelopment of GPRA Colony at Netaji Nagar - Construction of Type - VII & VIII Qtr. (199 Nos): ₹659 Crore
- Redevelopment of GPRA Colony at Netaji Nagar - Construction of Type –V quarters (540 Nos): ₹616 Crore
- Redevelopment of GPRA Colony at Sarojini Nagar – Construction of Residential Apartments(99 Nos): ₹363 Crore
- Development of Residential Towers and Community Center at 37-D, Green View Apartments, Gurugram: ₹821 Crore
- Construction & Development at Central University of Odisha, Sunabeda: ₹442 Crore
- Construction of Prashashan Stambh, Goa: ₹263 Crore
- Execution of African Zoo, Safari Plaza at Gorewada International Zoological Park, Nagpur: Value not specified
- Construction of campus for Indian Institute of Foreign Trade (IIFT) at Maidan Garhi, New Delhi: ₹289 Crore
Redevelopment Business Model
NBCC specializes in redevelopment on self-sustainable basis, providing solutions to stalled real estate projects through three models:
- Model 1: Outright sale of part of land (e.g., Moti Bagh)
- Model 2: Long term lease of part BUA (e.g., East Kidwai Nagar)
- Model 3: Freehold Sale of part BUA (7 GPRA)
Process involves demolishment of old structures and construction of new sites with modern amenities, with funds generated through commercial exploitation.
Major Redevelopment Projects
7 GPRA Colonies Redevelopment:
- Nauroji Nagar
- Kasturba Nagar
- Netaji Nagar
- Thyagraj Nagar
- Sarojini Nagar
- Srinivaspuri
- CPWD – Central Public Works Department
Marketing & Sale of 7 GPRA Projects:
- WTC Nauroji Nagar: 3.15 Lakh sqm BUA, ₹13,884 Crore total sale, 100% Sold
- Commercial Block 'Downtown' - Sarojini Nagar: 0.32 Lakh sqm, ₹1,403 Crore, 37% sold (bulk sale to Mansan Group)
- Bharat Business Park, Sarojini Nagar: 2.17 Lakh sqm, ₹9,168 Crore, 62.5% sold
- Residential Apartments (500 Nos) at Vinayak Mandir Marg: 1.31 lakh sqm, ₹5,513 Crore - Yet to be launched
- Residential Apartments (99 Nos) at Scindia Marg: 0.57 lakh sqm, ₹2,417 Crore - Yet to be launched
- Residential Apartment along Africa Avenue (262 flats): 1.07 lakh sqm, ₹4,519 Crore - Yet to be launched
Amrapali Projects Completion
- In 2019, Supreme Court assigned work to NBCC on PMC Basis to complete left-over work of erstwhile Amrapali Group
- 25 projects in Noida & Greater Noida
- NBCC has completed more than 32,550 houses
- Total number of Units under NBCC's scope: 38,000
- Sanctioned value of project: ₹8,373 Crore
- Received ₹12,500 Crore work to develop unused FAR at 6 locations
- Additional 8,269 houses being constructed
- Auctioned bulk sale of 6 FAR projects (5,803 residential units)
- Units sold in FY 2025-26: 4,625 nos. with sale value of ₹9,366 Crore
- ₹1,500 crore additional/top-up loan facility sanctioned from State Bank of India
International Projects
- New Supreme Court Building at Port Louis, Mauritius: USD 42 Million/INR 210 Cr.
- Mahatma Gandhi International Convention Centre at Niger: USD 56 Million/INR 400 Cr.
- Institute for Security & Law Enforcement Studies at Addu City, Maldives: USD 33.00 Million/INR 262 Cr.
- Social Housing Project at Mare Tabac & Dagotiere, Mauritius: USD 46.5 Million/INR 210 Cr.
- Construction of Indian Pavilion at World Expo 2020, Dubai: USD 46.8 Million/INR 280 Cr.
- Social Housing Project at Hulhumale Maldives: USD 130 Million/INR 1,179 Cr. (2,000 units)
Recent Developments
Supertech Project:
- Supreme Court upheld NCLT order appointing NBCC to complete stuck Supertech housing projects
- 50,000 stalled units across 16 projects in UP, Haryana, Uttarakhand, and Karnataka
- Estimated Top-line: ₹10,000 crore
- Self-sustainable revival model without deploying NBCC's own balance sheet funds
Ghitorni Project - Delhi Land Dispute Resolution:
- NBCC settled long-standing land dispute in Delhi
- 21.23 acres (4.45 lakh sq. meters of built-up area)
- Estimated revenue potential: ₹8,500 crore
- ₹220 Cr. paid to Govt. of NCT of Delhi towards land premium and ground rent
- Leasing of land in favour of NBCC in progress
Dubai Real Estate Entry:
- NBCC entered Dubai real estate market with ~15 million AED (approx. ₹37 crore) land purchase
- 14,776 sq ft in Dubai Mainland for mixed-use project
- Through NBCC Overseas Real Estate LLC (wholly owned subsidiary)
- Expected Sale: ₹175 Cr with Saleable Area of 51,716 sq ft
Overseas Partnerships & Work:
- BCD Global Project Management Pact (April 2026): PMC for residential development in Warsan district, Dubai
- Pantheon Elysee Real Estate Mega MoU (November 2025): Joint construction of projects across UAE
- Republic of Seychelles Housing Order (April 2026): PMC for social housing in Seychelles
- Goldfields Australia Real Estate MoU (November 2025): Co-development of infrastructure in Australia
Way Forward: Opportunities
Domestic opportunities:
- Redevelopment/Monetization Govt./State Govt. land
- GPRA Colonies
- CPSE land Monetization
- Border Fencing Works
- Stalled Real Estate Projects
- Health Infrastructure Projects
- Ports, Highways, Road infrastructure
International opportunities:
- Make in India GOI thrust for boosting exports
- Multilateral Funding Agencies commitments in South Asia & Africa
Strategic Actions:
- Order Book Conversion into Running Projects
- Faster & Quality Construction with new technology
- Oversees Expansion
- Construction of Ghitroni Project (Real Estate)
- Fast Track Execution of GPRA & Amrapali Phase 2 Project
- Real Estate Sale/Marketing in Redevelopment Projects
Board of Directors
- Shri K. P Mahadevaswamy - Chairman & Managing Director (32+ years experience)
- Shri Ravi Kumar Arora - Govt. Nominee Director (IAS, Joint Secretary Land & Estates, MoHUA)
- Shri Sanjeet - Govt. Nominee Director (Joint Secretary & Financial Advisor, MoHUA)
- Shri Vishal Puri - Independent Director (Ex-Chairman of Chandigarh Branch of ICAI)
- Dr. Suman Kumar - Director (Commercial) (30+ years in Civil Engineering)
- Shri Anjeev Kumar Jain - Director (Finance) (30 years in finance and accounts)