Parbati-II: Reported a loss of ₹150 crore for FY26, but a profit of ₹104 crore in Q4 FY26 after booking a ₹200 crore shortfall in energy revenue.
Subansiri Lower (SLP): Reported a profit of ₹495 crore for FY26, with ₹487 crore earned in Q4 FY26.
Revenue Under-Recovery: Approximately ₹300 crore for Parbati-II and ₹150 crore for Subansiri Lower, as revenue is booked at 80% of filed AFC pending CERC tariff orders.
Dividend
The Board recommended a final dividend of ₹0.21 per share (2.10%) for FY26.
This is in addition to the interim dividend of ₹1.40 per share (14%) already paid.
Total dividend for FY26 is ₹1.61 per share (16.10%) on face value of ₹10.
Project Updates & Operational Highlights
Commissioned Projects
Subansiri Lower (2,000 MW): Four units (250 MW each) commissioned. Remaining four units expected by March 2027. Total anticipated cost: ₹30,072 crore. Expenditure incurred till March 2026: ₹26,092 crore.
Parbati-II: Commissioned and contributing to generation.
Karnisar Solar: Commissioned.
New Project Approvals & Agreements
Uri-I Stage-II (240 MW) & Dulhasti Stage-II (260 MW): Investment approval accorded by NHPC Board on February 20, 2026 (Cost: ₹2,709 cr & ₹2,994 cr). Implementation agreement signed with J&K SPDCL on March 27, 2026. Civil contracts awarded in March 2026. Scheduled completion: November 2029.
Kamala HE Project (1,720 MW): CCEA approved investment of ₹26,070 crore on April 8, 2026. To be implemented via JV with Govt. of Arunachal Pradesh. Subsidiary formation and clearances in process.
Under-Construction Project Status
Dibang Multipurpose (2,880 MW): All major contracts awarded, including dam package (₹14,446 cr) in April 2026. Estimated cost: ₹31,876 crore (includes ₹6,716 cr grant). Expenditure incurred: ₹4,504 crore (Mar'26). Scheduled completion: February 2032.
Rangit-IV (120 MW) - JPCL: 96% physical progress. Boxing up of all three units completed. Estimated cost: ₹1,889 cr. Expenditure: ₹1,792 cr (Mar'26). Expected commissioning: November 2026. Merger process with NHPC ongoing; second motion application filed with MCA.
Ratle HE (850 MW): 29% physical progress. Estimated cost: ₹5,282 cr. Expenditure: ₹1,538 cr (Mar'26). Expected commissioning: November 2028.
Teesta-V Restoration: Under progress. Expected to start generation in June 2026.
Solar Projects
CPSU Scheme, Tranche-II (1,000 MW): 300 MW in Bikaner, Rajasthan commissioned. 100 MW in Andhra Pradesh expected by June 2026. 600 MW in Gujarat expected by December 2026.
Other Solar: 40 MW in Ganjam, Odisha expected by October 2026. 50 MW Floating Solar in Kerala expected by March 2027.
Gujarat Solar (Khavda RE Park): 200 MW (Stage-I & Stage-III) expected by June 2026 and December 2026, respectively.
Future Pipeline
Exploring Pumped Storage Projects (PSPs) in Maharashtra, Odisha, MP, Gujarat, Chhattisgarh, Rajasthan, Andhra Pradesh. 18 GW PSPs at DPR/PFR stage.
Expecting to start construction of Indira Sagar-Omkareshwar PSP (640 MW) in FY27.
Actively pursuing Sawalkot (1,856 MW), Subansiri Upper (1,605 MW), and Etalin (3,097 MW) at different clearance stages.
Target to bring five hydro projects into construction in FY27: Uri-I S-II, Dulhasti S-II, Etalin, Sawalkot, Kamala, and one PSP (Indira Sagar-Omkareshwar).
Key Operational Metrics
Normative PAF: Consolidated 82%, Standalone 80%.
FY26 PAF (ex-Teesta-V): 80%.
Realization: Received ₹10,499 crore from beneficiaries against energy sale in FY26 (vs. ₹9,943 cr in FY25).
Net Receivables Breakdown: Billed Receivables: ₹743 cr; Less dues converted to installments: ₹39 cr; Net amount due: ₹704 cr; Dues >45 days: ₹242 cr.
Tariff & Regulatory Matters
Parbati-II: Interim tariff order from CERC received (billing at 75% of filed tariff). Final hearing scheduled for May 25, 2026; order expected by end-June 2026.
Subansiri Lower: Tariff petition filed with CERC. Awaiting interim tariff order. Final order expected within ~6 months of interim order.
Deferred Tax Adjustment: Opted for lower tax regime (25% under Sec. 115BAA). Reversed DTL created at higher rate, resulting in a net impact of ~₹900 crore on PAT (disclosed in Note #8 of financials).
Q&A Highlights
Adjusted PAT: Reported PAT includes a one-off tax benefit of ~₹900 crore. Adjusted PAT is approximately ₹900 crore lower.
Teesta-V Impact: No revenue contribution in FY26. Expected AFC is ~₹500 crore (~₹400 cr ex-tax). Generation expected to resume June 2026.
Regulated Equity: Current regulated equity (incl. Parbati-II): ₹18,309 crore. Expected hydro regulated equity by end-FY27: ₹30,672 crore with the commissioning of ~2,994 MW hydro and ~1,190 MW solar.
Cost Escalation: Inherent in hydro projects due to price variation clauses. CERC allows pass-through of costs beyond management's control.
Generation Shortfall Booking: Regulation allows billing for shortfall in design energy if reasons are beyond control (e.g., applied for Parbati-II).