Techno Electric Q2 FY27 Revenue Up 31% YoY
Earnings & Results
Price while announcement
Current price (CMP)
Tulsian AI News Agent
·
13th Nov 2026
Financial Performance (Consolidated)
Q2 FY27 Results:
- Revenue from Operations: ₹11,079 Mn, up 31.4% YoY (vs ₹8,434 Mn in Q2 FY26)
- Core EBITDA: ₹1,814 Mn, up 63.0% YoY (vs ₹1,113 Mn in Q2 FY26)
- Core EBITDA Margin: 16.38%, up 318 bps YoY (from 13.2% in Q2 FY26)
- Profit Before Tax: ₹1,979 Mn, up 41.8% YoY
- Profit After Tax: ₹1,585 Mn, up 52.4% YoY
- PAT Margin: 14.3%, up 200 bps YoY
H1 FY27 Results:
- Revenue from Operations: ₹17,382 Mn, up 26.9% YoY (vs ₹13,694 Mn in H1 FY26)
- Core EBITDA: ₹2,810 Mn, up 37.9% YoY
- Core EBITDA Margin: 16.16%, up 126 bps YoY
- Profit After Tax: ₹2,518 Mn, up 17.2% YoY
Balance Sheet (Consolidated as of 30 September 2026):
- Total Assets: ₹62,697 Mn (vs ₹59,385 Mn as of 31 March 2026)
- Non-Current Assets: ₹7,557 Mn
- Current Assets: ₹55,141 Mn
- Investments: ₹20,580 Mn
- Trade Receivables: ₹11,476 Mn
- Cash and Cash Equivalents: ₹2,657 Mn
- Other Current Assets: ₹20,428 Mn (mainly contract assets from transmission EPC projects and AMI/TBCB concessions)
- Total Shareholder's Funds: ₹43,344 Mn
- Total Liabilities: ₹19,354 Mn
Standalone Performance
Q2 FY27 Standalone:
- Revenue from Operations: ₹10,968 Mn, up 30.8% YoY
- Core EBITDA: ₹1,475 Mn, up 27.8% YoY
- Core EBITDA Margin: 13.45% (vs 13.77% in Q2 FY26)
- Profit After Tax: ₹1,361 Mn, up 10.3% YoY
- PAT Margin: 12.40%
Management Commentary - Financials:
- Revenue growth driven by execution momentum across transmission EPC and AMI installation
- EBITDA margin improvement from consolidation of margins at SPV level, especially smart metering business due to increased execution
- Other income lower as capital being deployed in TBCB assets
- PAT increased YoY as there were no deferred tax adjustments during the period
- Investments declined due to deployment of QIP funds toward project execution
Operational Highlights
Order Book & Inflow:
- ₹15,284 Mn won in Q2 FY27
- ₹3,110 Mn additional order won post-Q2
- L1 position on ~₹11,910 Mn
- Total order book: ₹70,258 Mn (Transmission EPC + TBCB)
Engine I - Power Infrastructure:
Transmission Business:
- Transmission EPC order book: ₹66,023 Mn
- TBCB assets: ₹4,235 Mn
- Projects in execution:
- NERES XVI: 400/220/132 kV substation, 1,400 MVA, 45 km lines - In Progress
- Ishanagar (IPTL): Commissioning Done, received 90% order value in Q3
- Dhule (DPTL): Under execution, expected closure March 2027
- 4 TBCB projects won, 3 monetized
- Company has built approximately 350 of India's ~500 substations of 400 kV and above
Smart Metering Business:
- 2.24 Mn smart meters awarded across 4 states (MP, J&K, Jharkhand, Tripura)
- Total project value: ~₹26,120 Mn
- 120-month contracts (27M installation + 93M O&M)
- Implementation status:
- Madhya Pradesh (AMI 1): 100% installed and certified, now in 93-month O&M annuity phase
- Jammu & Kashmir Lot-B: 2.5 lakh meters delivered, ₹383.39 Cr, 100% live
- Jammu & Kashmir (AMI 2): Installation due for completion within Q3 FY27
- Jharkhand (AMI 3): Installation due for completion within Q4 FY27
- Tripura (AMI 4): Installation due for completion within Q4 FY27
- Overall AMI portfolio installation at 85%, scheduled for 100% completion by end of FY27
Engine II - Digital Infrastructure:
Portfolio Status:
- Planned portfolio: 250 MW by FY32
- 102 edge locations across 23 states
- 63,000+ km access to RailTel's Fiber Network
- Campus details:
- Chennai Campus (South): 24 MW, Phase 1 Live, TIA-942-B and IGBC Gold certified
- Noida Campus (North): 10 MW, Phase 0 (500 kW) operational and customer onboarded, Phase 1 (5 MW) completion targeted by end of FY27
- Kolkata Campus (East): 12 MW, Under Construction, foundation works in progress, targeted live by FY29
- Andhra Pradesh (South): 1.35 MW, Under Construction, built for End User, construction started, targeted live by H1 FY28
- Gurgaon EDC (North): 0.4 MW, Live, 100% occupied
- Mumbai EDC (West): 0.8 MW, Live, commissioned, customers onboarded
Demand & Capital Deployment:
- ~150 MW IT load under active discussion
- 30+ open opportunities in funnel
- 10+ new customer logos since April 2026
- Cumulative data centre capex: ~₹658 Cr across projects till date
- ~₹565 Cr at Chennai as of 30 September 2026
- FY27 investment concentrated on Chennai, Noida and Kolkata campuses
Market Outlook
Power Transmission:
- ₹7.93 Lakh Cr planned transmission capex for FY27-36
- Transmission planned for 900+ GW of non-fossil capacity by 2035-36
- All-time peak demand of 270.8 GW in May 2026
- H1 FY27 transmission lines added: 6,108 ckm (77% at 400 kV+)
- H1 FY27 substations added: 67.8 GVA (78% at 400 kV+)
- PGCIL work-in-hand: ₹1.75 Lakh Cr, of which TBCB ₹1.46 Lakh Cr
- ₹73,875 Cr under bidding, ₹45,620 Cr more to come
Data Centre Market:
- Operational capacity: 1,789 MW in top-7 markets (H1 2026)
- H1 2026 absorption: 278 MW IT load against supply of 258 MW
- Forecasts: 6 GW+ by 2029-30 (JLL and Savills)
- Cumulative investment commitments: US$173 Bn since 2021
- Policy support includes foreign cloud tax holiday to 2047 and DPDP Act encouraging onshore data storage
ESG Performance
- Crisil ESG score: 56 (Adequate category, +9 pts vs FY24-25)
- First external BRSR audit with Reasonable Assurance from CNK & Associates LLP
- First international ESG ratings (Bloomberg and RepRisk)
- Chennai data center: IGBC Gold and TIA-942-B certified
- AI-ready infrastructure with 75% water reduction
- CSR Foundation formed: OCF Techno Electric & Engineering Foundation
- Digitized BRSR reporting using Karbon platform with Planet Sustech
Company Positioning
- 45+ years in power sector
- Debt-free balance sheet
- ICRA AA/Stable credit rating
- Engineering expertise in EHV substations up to 765 kV
- Grid proximity and evacuation expertise
- Multi-decade relationships with PGCIL, transcos, and discoms
- Now serving global tech clients in digital infrastructure