Summary of Key Information:

Reporting Period: Quarter and Year ended March 31, 2026

Nature of Filing / Announcement: Financial Results pursuant to Regulation 33 of SEBI (LODR) Regulations, 2015

Date of Board Meeting / Approval: May 30, 2026 (commenced 12:00 PM, concluded 5:15 PM)

Audit Opinion: Unmodified Opinion with Emphasis of Matter

Auditor's Comment: Material uncertainty relating to going concern due to delayed realization of receivables resulting in severe cash crunch

Key Financial Highlights [All amounts in Rupees Millions]

Standalone Results:

Revenue from Operations:

  • Q4 FY26: ₹1,016.24 (vs Q4 FY25: ₹4,050.58) -75% YoY
  • FY26: ₹8,511.95 (vs FY25: ₹12,374.18) -31% YoY

Total Income:

  • Q4 FY26: ₹1,045.33
  • FY26: ₹8,613.95

Net Profit/(Loss):

  • Q4 FY26: ₹(1,307.90) loss
  • FY26: ₹(1,501.16) loss (vs FY25: ₹585.96 profit)

EPS:

  • Q4 FY26: ₹(10.49)
  • FY26: ₹(12.04) (vs FY25: ₹4.70)

Other Equity: ₹5,053.06 (vs FY25: ₹6,546.66) -23%

Cash and Cash Equivalents: ₹8.16 (vs FY25: ₹53.38) -85%

Debt:

  • Short-term Borrowings: ₹5,900.94
  • Long-term Borrowings: ₹594.51
  • Total Debt: ₹6,495.45

Consolidated Elements:

The financial results include 21 jointly controlled operations incorporated on a proportionate basis:

  • Total assets: ₹1,251.76 million
  • Total revenue: ₹1,111.27 million
  • Net cash outflow: ₹47.16 million

Segment-wise Performance:

The company operates in a single segment: construction and infrastructure development in India

Corporate Actions:

Not Specified

Other Significant Information:

Contract Disputes and Exceptional Items:

1. Chief Engineer (Construction)-III, North Western Railway terminated contract "Jaipur - Sawai Madhopur Doubling Project" (T. No. NWR/SC/SWM-JP/Doubling/Civil-514110102) on January 13, 2026

  • Performance bank guarantee encashed and security deposit forfeited: ₹99.64 million
  • Provided as exceptional item in Q3 FY25 and FY26 results
  • Civil Writ Petition filed (S.B.C.W. No. 983/2026 & 8878/2026) before Rajasthan High Court, Jodhpur - pending final hearing

2. Chief Engineer (Construction-I) North West Railway Jaipur terminated contract "Major upgradation of Bikaner Railway Station" (Tender No. NWR-SC-BKN-16-2023-24-EPC) on May 11, 2026

  • Potential exposure: ₹199.472 million (performance bank guarantee + security deposit)
  • Civil Writ Petition filed (SBCWP No. 10651/2026) before Rajasthan High Court Jodhpur
  • Court has recorded undertaking from respondents that they will not proceed for encashment of Bank Guarantee until next hearing

Liquidity and Going Concern:

  • Company experienced severe cash crunch due to delayed realization of receivables from Government departments
  • Temporarily slowed down operations
  • Promoters provided support through unsecured interest-free loans
  • Repaid and closed borrowing facilities from banks and financial institutions aggregating approximately ₹3,340 crore during the year
  • Management expects recovery of receivables based on pending approvals, historical trends, and ongoing follow-up
  • Financial statements prepared on going concern basis

Joint Operations:

  • VPRPL-KALPATARU JV: Dispute with Kalpataru Enterprises (JV Partner) - no access to financials, not incorporated in results
  • 21 other jointly controlled operations included on proportionate basis

Labour Code Implementation:

  • Government consolidated 29 labour legislation into four codes effective from November 21, 2025
  • No material financial impact presently envisaged
  • Further evaluation pending notification of relevant rules