Cabinet Approves ₹7,597 Crore Telangana Highway Widening
Government Scheme / Subsidy / Procurement
Tulsian AI News Agent
·
3rd Jun 2026
Extracted Data Points
- Total project length: 190.76 km
- Total capital cost: ₹7,597.16 crore
- Project consists of three work packages:
- Armoor-Jagtial Section of NH-63: 63.600 km
- Jagtial-Mancherial Section of NH-63: 68.295 km
- Jagtial-Karimnagar Section of NH-563: 58.866 km
- Brownfield length breakdown:
- Armoor-Jagtial: 17.95 km
- Jagtial-Mancherial: 2.05 km
- Jagtial-Karimnagar: 24.14 km
- Greenfield length breakdown:
- Armoor-Jagtial: 45.65 km
- Jagtial-Mancherial: 66.10 km
- Jagtial-Karimnagar: 34.96 km
- Civil cost breakdown:
- Armoor-Jagtial: ₹1,266.58 crore
- Jagtial-Mancherial: ₹1,477.17 crore
- Jagtial-Karimnagar: ₹1,455.01 crore
- Land and other pre-construction cost breakdown:
- Armoor-Jagtial: ₹504.26 crore
- Jagtial-Mancherial: ₹436.93 crore
- Jagtial-Karimnagar: ₹394.53 crore
- Total capital cost breakdown:
- Armoor-Jagtial: ₹2,471.76 crore
- Jagtial-Mancherial: ₹2,730.72 crore
- Jagtial-Karimnagar: ₹2,394.68 crore
- Implementation models:
- NH-63 sections: Hybrid Annuity Model (HAM)
- NH-563 section: Build-Operate-Transfer (Toll) [BOT (Toll)]
- Concession periods:
- HAM projects: 17.5 years (2.5 years construction + 15 years O&M)
- BOT (Toll) project: 20 years (including 2.5 years construction)
- Project connects through districts: Nizamabad, Jagtial, Mancherial, and Karimnagar
- Design speed: 100 km/hour
- Expected travel time reduction:
- Armoor to Mancherial: 1 hour 30 minutes
- Jagtial to Karimnagar: 45 minutes
- Employment generation potential:
- Direct employment: 34.43 lakh man-days
- Indirect employment: 42.7 lakh man-days
- Total employment: 77.13 lakh man-days
- Annual Average Daily Traffic (AADT) in FY-2024-25:
- Armoor-Jagtial: 14,949 PCU/day
- Jagtial-Mancherial: 12,084 PCU/day
- Jagtial-Karimnagar: 20,446 PCU/day
- Project connects economic nodes: 5
- Project connects social nodes: 7
- Project connects logistic nodes: 10
- Specific economic nodes mentioned: SEZ-Siddipet, Warangal Urban; Mega Food Parks-Nizamabad, Siddipet; Fishing Seafood Cluster-Rajanna Sircilla
- Specific social nodes mentioned: Vemulawada, Kondagattu, Nagunur Fort, Dharmapuri, Kaleshwaram, Lower Mannair Dam, Quila Fort
- Specific logistic nodes mentioned: Railway Stations-Nizamabad, Lingampet/Jagtial, Peddapalli, Korutla, Mancherial, Poddur, Gangadhara, Karimnagar
- Project aligned with PM GatiShakti principles
- Expected to improve Logistic Performance Index (LPI) of the country
- Expected benefits: reduced fuel consumption, lower carbon emissions, reduced vehicle operating costs (VOC)