Extracted Data Points:

  • Total project length: 190.76 km
  • Total capital cost: Rs. 7597.16 crore
  • Project consists of three work packages
  • Armoor-Jagtial Section of NH-63: 63.600 km length
  • Jagtial-Mancherial Section of NH-63: 68.295 km length
  • Jagtial-Karimnagar Section of NH-563: 58.866 km length
  • Armoor-Jagtial Section brownfield length: 17.95 km
  • Armoor-Jagtial Section greenfield length: 45.65 km
  • Jagtial-Mancherial Section brownfield length: 2.05 km
  • Jagtial-Mancherial Section greenfield length: 66.10 km
  • Jagtial-Karimnagar Section brownfield length: 24.14 km
  • Jagtial-Karimnagar Section greenfield length: 34.96 km
  • Armoor-Jagtial Section total civil cost: Rs. 1266.58 crore
  • Jagtial-Mancherial Section total civil cost: Rs. 1477.17 crore
  • Jagtial-Karimnagar Section total civil cost: Rs. 1455.01 crore
  • Armoor-Jagtial Section land and pre-construction cost: Rs. 504.26 crore
  • Jagtial-Mancherial Section land and pre-construction cost: Rs. 436.93 crore
  • Jagtial-Karimnagar Section land and pre-construction cost: Rs. 394.53 crore
  • Armoor-Jagtial Section total capital cost: Rs. 2471.76 crore
  • Jagtial-Mancherial Section total capital cost: Rs. 2730.72 crore
  • Jagtial-Karimnagar Section total capital cost: Rs. 2394.68 crore
  • NH-63 sections to be developed on Hybrid Annuity Model (HAM)
  • NH-563 section to be developed on Build-Operate-Transfer (Toll) [BOT (Toll)]
  • HAM concession period: 17.5 years (2.5 years construction + 15 years O&M)
  • BOT (Toll) concession period: 20 years (including 2.5 years construction)
  • Design speed: 100 km/hour
  • Project connects five Economic Nodes, seven Social Nodes and ten Logistic Nodes
  • Employment generation: 34.43 lakh man-days (direct) & 42.7 lakh man-days (indirect)
  • Annual Average Daily Traffic (AADT) in FY-2024-25: Armoor-Jagtial - 14,949 PCU/day
  • Annual Average Daily Traffic (AADT) in FY-2024-25: Jagtial-Mancherial - 12,084 PCU/day
  • Annual Average Daily Traffic (AADT) in FY-2024-25: Jagtial-Karimnagar - 20,446 PCU/day
  • Expected travel time reduction: 1 hour 30 minutes between Armoor and Mancherial
  • Expected travel time reduction: 45 minutes between Jagtial and Karimnagar
  • Project passes through Nizamabad, Jagtial, Mancherial, and Karimnagar Districts
  • Built-up areas along corridor: Anksapoor, Korutla, Jagtial, Dharmapuri, Lakshettipet, Mancherial, Potharam, Gangadhara, Karimnagar
  • Project aligned with PM GatiShakti principles
  • Expected to improve Logistic Performance Index (LPI) of the country
  • Expected substantial reductions in fuel consumption, carbon emissions, and vehicle operating costs (VOC)