Authority: High Court of Odisha, Cuttack
Order Date: 06 November 2026
Case Overview
- Petitioner: ACREWISS Developers Private Ltd, represented by Advocate M.R. Baug.
- Opposite parties: State of Odisha and another party, represented by Additional Government Advocate D. Lenka.
- The petition sought disposal of four pending demarcation applications numbered 2026200201021, 2026200201035, 2026200201019, and 2026200201016.
- The matter was heard in hybrid mode before Justice Sashikanta Mishra.
Final Outcome
- The Court directed the Tahasildar, Bhubaneswar, to conclude all four demarcation applications as early as possible, preferably within four weeks from the date the petitioner receives a certified copy of this order.
Topics: Legal Order, Land Demarcation