Authority: National Company Law Appellate Tribunal, Principal Bench, New Delhi

Order Date: 13 August 2026

Case Overview

This order pertains to Comp. App. (AT) (Ins) No. 1496 of 2026 and an interlocutory application (I.A. No. 5750 of 2026). The appellant is Arainfra Projects Private Limited, and the respondents are Vakati Balasubramanyam Reddy & Anr. The matter before the tribunal is an application (I.A. No. 5750 of 2026) filed by the appellant praying for condonation of delay in filing the appeal. The appellant stated a delay of 26 days in their application. However, the Registry of the tribunal has calculated and recorded the delay as being 8 days, creating a discrepancy.

Final Outcome

The tribunal, comprising Officiating Chairperson Justice Yogesh Khanna and Members Barun Mitra and Ajai Das Mehrotra, did not rule on the condonation of delay. Instead, it directed the appellant to file a proper application for condonation of delay that accurately reflects the correct period. The appeal, along with this application, was adjourned and listed for the next hearing on 24 August 2026.

Topics: NCLAT, Legal Procedure, Delay Condonation