Banswara Syntex Limited has submitted a regulatory disclosure under SEBI Listing Regulation 30 regarding environmental compliance actions taken against its industrial unit.

The disclosure concerns an inspection conducted by the Pollution Control Committee of U.T. Administration of Dadra and Nagar Haveli and Daman and Diu (DNH&DD) at the company's industrial unit located at Survey No. 81, 82/1, 90/1 and 90/2, Daman Industrial Estate, Village Kadaiya, Daman-396210 (UT).

Authority Details

  • Name of Authority: Pollution Control Committee of U.T. Administration of Dadra and Nagar Haveli and Daman and Diu (DNH&DD)
  • Date of Order/Communication: 25th August, 2026
  • Date of Receipt: 25th August, 2026

Nature of Actions Taken

1. Directed the unit to comply with applicable provisions of:

  • Water (Prevention and Control of Pollution) Act, 1974
  • Air (Prevention and Control of Pollution) Act, 1981
  • Hazardous and other Waste (Management and Transboundary Movement) Rules, 2016

2. Required corrective measures to ensure compliance with environmental norms prescribed by PCC DNH & DD

3. Imposed Environmental Compensation of ₹1.47 Crore

Violations/Observations

During the inspection, authorities observed the following violations:

  • The installed Dust Collector System was found to be inadequate
  • Fugitive emission from stack of boiler was above prescribed emission standards
  • Non-compliance with stack emission standards as per Consent to Operate and applicable CPCB/PCC norms
  • Lack of clearly demarcated Hazardous Waste storage area with proper labelling and necessary safety arrangements

Financial Impact

The financial impact is quantified as the Environmental Compensation levied and paid, amounting to ₹1.47 Crore. The company has paid this amount on 25th August, 2026.

Company Response

The company has initiated necessary corrective measures as per the directions of the Pollution Control Committee.