Authority: Supreme Court of India

Order Date: 19-11-2026

Case Overview

  • Petitioner: Brick Rise Developers Pvt. Ltd.
  • Respondents: State of Uttar Pradesh and others (IA Nos. listed)
  • The petition arose from an impugned final judgment and order dated 24-02-2025 in WRITC No. 15604/2021 passed by the High Court of Judicature at Allahabad.
  • The dispute concerned compliance with payment obligations and regulatory conditions for plot SC-02/H&I in Noida, including a lien requirement under condition no.12 of the earlier order dated 24.11.2025 (SLP [C] No. 6118/2025).
  • Counsel for the petitioner and the Solicitor General for the respondents were heard before Hon'ble Mr. Justice M.M. Sundresh and Hon'ble Mr. Justice Prasanna B. Varale.

Final Outcome

1. The Court held that all payments due for plot SC-02/H&I have been fully paid to Noida, with compliance of any sports‑facility requirements confirmed by Noida. Consequently, condition no.12 imposed by the order dated 24.11.2025 is not applicable, and there is no requirement to create a lien on 20% of units of each constructed tower on the plot.

2. Noida shall grant conditional occupancy certificates for the pending applications within four weeks from the date of this order, subject to the final outcome of the Special Leave Petitions and any further directions of this Court.

3. All consequent and necessary approvals required for completion of the project on plot SC-02/H&I shall be granted by Noida within six weeks from today, in accordance with law.

4. Registration of conveyance deeds for those units where conditional occupancy certificates have been received shall commence at the earliest; Noida shall facilitate the tri‑party registration process with the applicant and home‑buyers within six weeks from today.

5. IA No. 74246/2026 is hereby disposed of.

Topics: Real Estate, Court Order