Authority: Supreme Court of India

Order Date: 19-08-2026

Case Overview

  • Petitioner: BSES Yamuna Power Ltd.
  • Respondent: Delhi Electricity Regulatory Commission.
  • The petition sought an extension of time for the Appellate Tribunal to dispose of the underlying case.
  • Earlier, the Court on 12‑05‑2026 ordered the Tribunal to dispose within two months.
  • The Tribunal subsequently requested additional time.

Final Outcome

  • The Court extended the disposal period by an additional two months.
  • Consequently, all miscellaneous applications were disposed of.

Topics: Regulatory Extension, Power Sector