Authority: High Court at Calcutta, Commercial Division

Order Date: 3 July 2026

Case Overview

  • Plaintiff: BST Infratech Limited; Defendant: Gammon Engineers and Contractors Pvt. Ltd.
  • The suit (CS‑COM/392/2024, old no. CS/145/2022) concerned a claim of Rs 64 lakhs (principal sum inclusive of interest).
  • Parties initially proposed different instalment plans (plaintiff: two instalments of Rs 32 L; defendant: four instalments of Rs 16 L) but later agreed on a three‑instalment settlement.
  • The agreed instalments: Rs 20 L on 15 July 2026, Rs 20 L on 16 August 2026, and Rs 24 L on 17 September 2026.

Final Outcome

  • By consent, the decree directs the defendant to pay the total Rs 64 lakhs in the three instalments specified above.
  • If any instalment is not paid on time, the consent decree becomes immediately executable.
  • No further coercive action may be taken by the plaintiff if the payment schedule is adhered to.
  • The suit and all pending applications are disposed of.

Topics: Civil Settlement, Construction Dispute