Authority: Supreme Court of India (Civil Original Jurisdiction)

Order Date: 24 September 2026

Case Overview

  • Parties: CEC‑SAM INDIA (NC-02) JV (Petitioner) vs. Delhi Metro Rail Corporation (Respondent).
  • Petition: Arbitration Petition No.71/2026 filed in the Supreme Court; reference made to Arbitration Petition No.66/2026 dated 15 September 2026 and Petition No.67/2026.
  • Background: The petitioner had deposited Rs 15,000 for each of the three arbitration petitions (Nos. 66, 67, 71) towards the appointment of an arbitrator.
  • Court Composition: Chief Justice Surya Kant, Justice Joymalya Bagchi, Justice V. Mohana.
  • Counsel for Petitioner: Mr. Samudra Sarangi, Ms. Riya Kalra, Mr. Vansh Dhall, Mr. Azmat Hayat Amanullah, AOR Ms. Rebecca Mishra.
  • Counsel for Respondent: Mr. Tarun Johri, AOR Mr. Ankur Gupta, Mr. Vishwajeet Tyagi.
  • Procedural Note: The order is digitally signed by Registrar Nitin Talreja on 29 September 2026 (signature not verified).

Final Outcome

  • The petition is dismissed in accordance with the earlier order dated 15 September 2026.
  • The Registry is directed to refund Rs 45,000 to the petitioner, calculated at Rs 15,000 per petition for Nos. 66, 67 and 71.
  • The petitioner is granted liberty to approach the jurisdictional High Court for any further relief.
  • Any pending applications, if any, are to be closed.

Topics: Arbitration, Court Order