Authority: Supreme Court of India

Order Date: 21 November 2026

Case Overview

  • Parties: Union of India & Ors (Petitioner) vs Himagiri Green Fields Pvt Ltd & Ors (Respondent).
  • Petition: Special Leave Petition (Civil) Diary No. 62230/2026 seeking condonation of delay in filing, arising from the impugned final judgment and order dated 08‑09‑2025 in WP No. 28677/2016 passed by the High Court for the State of Telangana at Hyderabad.
  • Hearing: The matter was called for hearing on 20‑11‑2026 before Hon'ble Mr. Justice J.B. Pardiwala and Hon'ble Mr. Justice K. Vinod Chandran.
  • Delay: The Court noted a gross delay of 302 days in filing the Special Leave Petition and found the petitioners' explanation unsatisfactory.
  • Merits: The Court observed that there was no good ground to interfere with the High Court's order dated 8 September 2025.

Final Outcome

  • The Special Leave Petition is dismissed on the ground of delay as well as on merits.
  • All pending applications, if any, are disposed of.

Topics: Legal Decision, Supreme Court, Special Leave Petition