Authority: National Company Law Tribunal (NCLT), Jaipur Bench

Order Date: June 18, 2026

Case Overview

This is a proceeding under Sections 397 and 398 of the Companies Act, 1956, which pertain to oppression and mismanagement in a company. The petitioners are Niranjan Lal Data & Ors., and the respondent company is M/s Data Ingenious Global Ltd. The case has a long history, with the original company petition (CP) numbered 53(ND) of 2009. A previous order dated March 12, 2026, had directed the parties to attempt mediation. However, upon interaction with the parties, the tribunal found that the matter could not be resolved through the mediation process.

Final Outcome

The mediation attempt was unsuccessful. The tribunal has posted the case for final arguments on the next date of hearing, which is October 1, 2026. The final ruling on the allegations of oppression and mismanagement is pending.

Topics: Shareholder Dispute, NCLT Proceeding, Corporate Governance