Date: 28th September, 2026
Project Update
Scheduled Commercial Operation Date Extension
- The Scheduled Commercial Operation Date (SCOD) of the company's project has been extended up to 31st December, 2026
- This is a continuation of previous disclosures made by the company, including reference to announcement dated 24th June, 2026
Current Project Status
- Installation of Plant and Machinery has been completed
- The project is at an advanced stage of commissioning
- Commencement of commercial operations is pending on account of certain statutory approvals
Pending Statutory Approvals
- Approval from Petroleum and Explosives Safety Organisation (PESO) in respect of ethanol storage
- Consent to Operate (CTO) from Madhya Pradesh Pollution Control Board (MPPCB)
Company Actions
- The company is actively pursuing the statutory approvals with respective authorities
- Taking all necessary steps to complete remaining regulatory and commissioning requirements
- Expects to commence commercial operations upon receipt of statutory approvals and completion of remaining formalities
- Will continue to keep Stock Exchanges informed of any material developments
Other Sections
- KMP / Board / Auditor Changes: Not Specified
- Dividend Declaration or Non-Declaration: Not Specified
- Board Meeting Outcomes: Not Specified
- Financial Results: Not Specified
- Auditor's Report: Not Specified
- Disinvestment / Strategic Actions: Not Specified
- Media Release / Investor Communication: Not Specified