Authority: Supreme Court of India
Order Date: 12-10-2026
Case Overview
- Petitioners: Earthin Projects Ltd, represented by counsel Ms. Aruna Gupta (AOR 1640) and Mr. Pranay Shridhar Chitale (AOR 3838).
- Respondents: IND Projects Limited, represented by counsel Ms. Bhavana Duhoon (AOR 3173).
- The matter (Miscellaneous Application Diary No(s). 66873/2025) involved applications for permission (IA No. 299545/2025) and intervention/impleadment (IA No. 304691/2025) related to default IA No. 299544/2025.
- Heard by Hon’ble Mr. Justice Alok Aradhe in chambers on 12 Oct 2026.
Final Outcome
- The Court granted the petitioner a four‑week period to cure the identified defects in the applications.
- The case was ordered to be listed again after the cure period.
Topics: Procedural Order, Civil Litigation