Authority: Supreme Court of India
Order Date: 16-07-2026
Case Overview
- Petitioner: Entegra Limited filed a miscellaneous application (Diary No. 64687/2025) seeking condonation of delay in filing a restoration application (IA No. 67504/2026) and restoration of the same.
- Respondents: Shree Maheshwar Hydel Power Corporation Ltd. and another party.
- Hearing Details: The matter was called for hearing on 16 July 2026 before Hon'ble Mr. Justice Satish Chandra Sharma, sitting in chamber.
- Legal Reference: The Court referred to the judgment delivered in Civil Appeal (Diary) No. 5988 of 2026, titled "CA Ramchandra Dallaram Choudhary vs. Adani Infrastructure and Developers Private Limited".
Final Outcome
- The Court, on a prima facie basis, ordered that both the restoration application and the application for condonation of delay be dismissed.
- The matter was directed to be listed before the Regular Court for further proceedings.
Topics: Court Order, Restoration Application