Authority: Supreme Court of India
Order Date: 03 July 2026
Case Overview
- Civil Appeals Nos. 8725‑8727/2026 filed by Global Energy Private Limited against Maharashtra Electricity Regulatory Commission and another respondent.
- Applications IA No. 184499/2026, IA No. 187084/2026, and IA No. 184498/2026 sought permission to file additional documents, facts, and annexures.
- The matter was heard by a two‑judge bench comprising Justice M.M. Sundresh and Justice Sheel Nagu on 3 July 2026.
Final Outcome
- The Court allowed the appellant to file the additional documents, facts, and annexures.
- A notice is to be issued, returnable on 8 September 2026.
- The respondent accepted the notice; the appellant must file a counter‑affidavit within four weeks and any rejoinder affidavit within two weeks.
Topics: Procedural Order, Regulatory Litigation