Authority: Supreme Court of India
Order Date: 17 November 2026
Case Overview
- Parties: Petitioner – Godrej Projects Development Limited; Respondents – Sandeep Sahi jwani & Anr.
- Proceedings: Civil Appeal Diary No. 9025/2026, heard on 16 November 2026 before Hon'ble Mr. Justice Sheel Nagu (in chamber).
- Background: Defects in the work undertaken by the petitioner were formally notified to the appellant on 27 February 2026. Despite the passage of eight months, the defects remained uncured.
- Counsel: For petitioner – Ms. Neha Agarwal, Adv. Mr. E. C. Agrawala (AOR 177). For respondents – Mr. Rishi Kapoor, Adv. Ms. Gitanjali Kapoor, Adv. Ms. Maitri Goal, Adv. Mr. Varun Ranjan, Adv. Mr. Ashish Kumar Upadhyay (AOR 3828).
Final Outcome
- The Court directed that the identified defects must be cured within a period of two weeks from the date of this order.
- The petitioner is required to pay a cost of Rs.5,000/- to the Supreme Court Legal Services Committee as a condition for the cure period.
- The matter is to be listed again after the two‑week period to verify compliance with the order.
Topics: Legal Dispute, Construction Defects