Authority: Supreme Court of India

Order Date: 17-11-2026

Case Overview

  • Petition for Special Leave to Appeal (C) No.18198/2026 filed by Haridwar Highways Project Limited against ERA Infra Engineering Limited & ANR, arising from the impugned final judgment and order dated 23-03-2026 of the High Court of Delhi in ARB.A.(COMM.) No.47/2025.
  • Multiple interim applications were listed: IA No. 218961/2026 (permission), IA No. 324566/2026 (appropriate orders/directions), IA No. 157696/2026 (exemption from filing C/C of the impugned judgment), IA No. 157706/2026, IA No. 269753/2026, IA No. 228911/2026, IA No. 162009/2026 (all seeking permission to file additional documents/facts/annexures), and IA No. 324226/2026 (document taken on record).
  • The bench comprised the Chief Justice, Justice Joymalya Bagchi and Justice V. Mohana. Counsel for the petitioner included Sr. Adv. Shyam Divan, Sr. Adv. Ritin Rai, Ms. Sushmita Gandhi, among others. Counsel for the respondent included Sr. Adv. Kapil Sibal, Sr. Adv. Mahesh Jethmalani, Sr. Adv. Dhruv Mehta, and a team of senior advocates.

Final Outcome

  • The Court heard arguments, reserved judgment, and granted both parties a week's time to file short written submissions.
  • An interim order was issued to continue the proceedings until the judgment is pronounced.

Topics: Legal Dispute, Infrastructure Contracts