Authority: Uttarakhand High Court, Hon'ble Manoj Kumar Tiwari, A.C.J.

Order Date: 27.11.2026

Case Overview

  • Applicant: M/s Kanswal Infra Pvt. Ltd.
  • Respondents: Public Works Department (Uttarakhand) and another party.
  • The application was filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of an arbitrator.
  • Kanswal Infra was awarded a contract for reconstruction work of Government Inter College, Paanjana, District Rudraprayag under the Rashtriya Madhyamik Shiksha Abhiyan. The tender was floated by the Public Works Department and the contract contains an arbitration clause (Clause 31.3).
  • The applicant alleges that the amount payable under the contract has not been paid and the security deposit lodged by it has not been released. A written notice dated 17.06.2025 requesting appointment of an arbitrator under the arbitration clause was sent, but no arbitrator was appointed.
  • Respondent counsel, Sri J.C. Pande, acknowledged the existence of the arbitration clause and the notice for appointment of an arbitrator.

Court's Observations and Directions

  • Considering the facts, circumstances, and the arbitration clause, the Court appoints Sri G.S. Dharmsaktu, retired District Judge (resident of 16 Rajeshwar Nagar, Phase‑I, Sahastradhara Road, Dehradun), as the sole arbitrator to resolve the disputes between the parties.
  • The seat of arbitration is fixed at Dehradun.
  • The arbitration application is allowed as per the terms stated.
  • The arbitrator must furnish his written disclosure to the Court within 15 days of receiving a certified copy of this order, as required by Section 11(8) of the Act.
  • The parties may determine the rules and procedure of arbitration in consultation with the arbitrator under Section 19 of the Act.
  • The arbitrator, in consultation with the parties, shall fix his remuneration and any other chargeable fees.
  • The arbitrator shall endeavour to hear the matter and pass an award within the time prescribed under the statute.

Final Outcome

  • Appointment of Sri G.S. Dharmsaktu as sole arbitrator, seat at Dehradun, with procedural directives for disclosure, rule‑making, remuneration, and timely award.

Topics: Arbitration, Public Works Contract