Authority: High Court of Chhattisgarh at Bilaspur

Order Date: 05 Oct 2026

Case Overview

  • Petitioner: Durga Prasad Khairwar, aged about 35, Office Assistant Grade‑I, Sub‑Division Pandariya, Chhattisgarh State Power Distribution Company Limited (CSPDCL).
  • Respondents: CSPDCL represented by its Managing Director, Executive Director (O/M), Superintendent Engineer, Assistant Engineer, and Executive Engineer of the Pandariya Division.
  • Petition: Writ Petition (WPS No. 7226 of 2026) seeking a direction to give effect to a transfer order dated 29‑May‑2026 and to relieve the petitioner so he can join the transferred posting.
  • Transfer Order (Annexure P/1): Issued by the Executive Director (O/M) Pandariya Division on 29‑May‑2026, transferring the petitioner from the Office of Executive Engineer (O/M) Division Pandariya to Office of Executive Engineer (O/M) Division‑II Bilaspur.
  • Petitioner’s Claim: Despite the transfer order, he has not been relieved and therefore cannot join the new posting; his representation to the employer yielded no action.
  • Respondent’s Argument: Cited lack of employees at the petitioner’s current posting as the reason for not relieving him.
  • Court’s Reasoning: The transfer order is an order of the competent authority, remains operative, and has not been cancelled, modified, or withdrawn. Administrative considerations cannot indefinitely withhold implementation of a valid transfer order.

Final Outcome

  • The Court held that the petitioner is entitled to the implementation of the transfer order dated 29‑May‑2026.
  • CSPDCL is directed to take necessary steps to relieve the petitioner and facilitate his joining at the Office of Executive Engineer (O/M) Division‑II Bilaspur within twenty (20) days of receipt of a copy of this order.
  • The writ petition is allowed to the aforesaid extent.

Topics: Employment, Transfer Order, Judicial Relief