Authority: High Court of Judicature at Bombay

Order Date: 7 October 2026

Case Overview

  • Applicants: Hitesh Constructions & Repairs & Ors.; Respondent: Cuffe Parade Sainara Premises Coop. Housing Society Limited.
  • Dispute arises from an Agreement dated 9 January 2023; arbitration clause in Clause 31.
  • Applicants invoked arbitration by serving notice on 3 June 2026.
  • Court found a valid, subsisting arbitration agreement and that it had been duly invoked.
  • Court ordered reference of the disputes to arbitration before a sole arbitrator.

Final Outcome

  • Mr. Aman Saraf, Advocate, appointed as Sole Arbitrator; office address: C/o. Mr. Rohan Savant, Room No.62, 5th Floor, Ali Chambers, Tamarind Lane, Fort, Mumbai 400001; email: aman.saraf292@gmail.com.
  • Parties to communicate contact particulars within one week; arbitrator to forward statutory Statement of Disclosure under Sections 11(8) and 12(1) to both sides within two weeks.
  • Parties to appear before arbitrator on dates he specifies and provide functional email and telephone numbers for service of notices.
  • Arbitration costs and fees to be borne equally by the parties, subject to adjustment by the final award.
  • The commercial arbitration application is disposed of as per the order.

Topics: Arbitration, Court Order