Authority: Court (presiding Judge Sandip Kumar De)
Order Date: 26 November 2026
Case Overview
- Petitioner: Smt. Malina Bhakta filed petition WPA 26997 of 2025 against Howrah Municipal Corporation and other respondents alleging unauthorized construction.
- Representation concerning the alleged construction was submitted to the Howrah Municipal Corporation on 12 September 2025 but was not considered.
- Counsel for Howrah Municipal Corporation appeared on 11 September 2026 but was absent on 12 November 2026; petitioner claimed the corporation refused to accept the notice.
- Private respondents (respondent nos.6 & 7) were present and asserted that the offending construction had already been demolished.
Final Outcome
- The Commissioner of Howrah Municipal Corporation (respondent no.2) is directed to consider the petitioner’s representation within four weeks from the date of the order.
- After hearing the petitioner and private respondents and reviewing submitted documents, the Commissioner must pass a reasoned order within one week of the hearing’s conclusion.
- If the demolition is found to be insufficient or only partial, the Commissioner may take further remedial steps immediately.
- The matter (WPA 26997 of 2025) is disposed of without any order as to costs; urgent photostat copies of the order may be issued upon compliance with formalities.
Topics: Unauthorized Construction, Municipal Regulation