Authority: High Court of Odisha at Cuttack
Order Date: 05.08.2026
Case Overview
- Petitioner: Siba Prasad Padhi, represented by Sr. Advocate A. Parija.
- Opposite Parties: Odisha Industrial Infrastructure Development Corporation (IDCO) and others.
- The petition seeks payment of dues owed for completing construction of a Planetarium building at Burla, pending for more than eight years.
- The matter was taken up in hybrid mode and the dues were admitted by the Court.
Final Outcome
- The writ petition is disposed of at the admission stage.
- The Court directs the Chief General Manager (Civil), IDCO, Bhubaneswar to consider the petitioner’s representation (Annexure‑10) and decide, in accordance with law, within two months of receipt of a certified copy of this order together with the writ petition.
- An urgent certified copy of the order shall be issued on proper application.
Topics: Legal Dispute, Infrastructure Payments