Authority: Supreme Court of India

Order Date: 13-07-2026

Case Overview

  • Petitioners: M/S Indus Residency Private Limited & Anr.
  • Respondents: Shailendra Sharma & Ors.
  • Origin: Petition for Special Leave to Appeal (C) No(s). 8485/2026 arising from the impugned final judgment and order dated 23-01-2026 passed by the High Court of Madhya Pradesh, Principal Seat at Jabalpur (MP No. 250/2026).
  • Core dispute: Determination of the monetary amount due from the petitioner to the respondents. An earlier order dated 20.04.2026 indicated a total liability of Rs 1,40,00,000/‑.
  • Payments made: The petitioner has paid Rs 70,00,000/‑, which the respondent’s counsel has admitted.
  • Counsel submissions: Senior counsel for the petitioner (Mr. S.K. Gangele) states that the remaining Rs 70,00,000/‑ will be paid within two months. Respondent counsel contends that the original total of Rs 1,40,00,000/‑ was mis‑calculated; after accounting for the Rs 70,00,000/‑ already paid, the correct balance should be approximately Rs 1,07,11,000/‑.

Final Outcome

  • The Court will consider the respondent’s objection after the petitioner pays the additional Rs 70,00,000/‑ within the next two months.
  • The matter is listed again for hearing on 21‑09‑2026.
  • By that date, the petitioner must place proof of the further payment before the Court.

Topics: Payment Settlement, Civil Litigation