Authority: Supreme Court of India

Order Date: 27-10-2026

Case Overview

  • Petitioner: Islamic Bank Bangladesh Limited (presently known as Islamic Bank Bangladesh PLC).
  • Respondents: Sushil Kumar More & Ors.
  • The petition arose from an impugned final judgment and order dated 03‑12‑2025 in AO‑COM No. 19/2025 passed by the High Court at Calcutta.
  • Special Leave Petition (Civil) Diary No. 13301/2026 sought condonation of delay in refiling/curing defects and challenged the High Court order.
  • Counsel for the petitioner and respondents appeared before a bench comprising Hon’ble Mr. Justice J.B. Pardiwala and Hon’ble Mr. Justice K. Vinod Chandran.

Final Outcome

  • The Supreme Court condoned the delay in refiling/curing defects.
  • It found no sufficient ground to interfere with the High Court’s impugned order.
  • Consequently, the Special Leave Petition was dismissed.
  • Any pending applications, if any, were disposed of.

Topics: Legal; Banking