Legal Proceedings Update:

  • JSW Energy Limited provides an update on material litigation concerning its subsidiaries
  • Subsidiaries involved: JSW Vayu (Tungabhadra) Private Limited, JSW Vayu (Indravati) Private Limited, JSW Wind Power (Pennar) Private Limited, and JSW Wind Power Limited
  • Previous disclosure reference: Dated 30th September 2023

Case Background:

  • Subsidiaries had filed appeals before the Appellate Tribunal for Electricity (APTEL)
  • Appeal was against Andhra Pradesh Electricity Regulatory Commission (APERC) order dated 18th October 2023
  • APERC order had directed AP Discom to pay Rs. 0.50 per unit for energy supplied beyond the prescribed Capacity Utilization Factor (CUF)

Recent Development:

  • APTEL issued its order on 17th November 2026
  • The appellate tribunal allowed the appeal filed by JSW subsidiaries
  • APTEL set aside the APERC order dated 18th October 2023

APTEL Directive:

  • APTEL directed AP Discoms to pay for energy generated by wind power generators at the applicable generic tariff
  • This payment directive applies irrespective of whether actual generation exceeds the normative CUF
  • APTEL also mandated payment of applicable interest in accordance with the respective Power Purchase Agreements

Regulatory Context:

  • Disclosure made under Regulation 30(4) of SEBI Listing Obligations and Disclosure Requirements Regulations, 2015
  • Refers to Regulation 30 of the Listing Regulations
  • Monica Chopra, Company Secretary