Other Operational / Legal / Strategic Disclosures
Material Litigation Outcome:
- JSW Hydro Energy Limited (JSWHEL), a material step-down subsidiary of JSW Energy Limited, had challenged an order dated 17 March 2022 passed by the Central Electricity Regulatory Commission (CERC)
- The CERC order disallowed JSWHEL's claim for notional interest during construction on equity in excess of 30% infused during construction (IDC Claim)
- The disallowance occurred during the truing-up of tariff for the period 2014-19 and determination of tariff for the period 2019-24
- The Appellate Tribunal for Electricity (APTEL) issued its order on 18th September 2026
- APTEL set aside the CERC order and allowed the IDC Claim of JSWHEL
- APTEL further held that carrying cost on such claim shall be reckoned from the date of filing of the true-up petition until its eventual adjustment
- The matter has been remanded to CERC to undertake prudence check of the data submitted in regard to additional IDC
- The financial impact of the allowed claim is ₹1,730 crore as determined by the tribunal
Regulatory Compliance:
- Disclosure made under Regulation 30(4) of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015
- Reference: Regulation 30 of the Listing Regulations
- Monica Chopra, Company Secretary of JSW Energy Limited
- Digitally signed on 19th September 2026 at 14:07:01 +05:30