Supreme Court granted special leave, dismissed Jyoti Infratech’s civil appeal against Madhya Pradesh, confirming interim stay on penalty recovery.
The dispute stems from termination of a bridge construction contract under NDB projects, with a Rs 10.27 cr penalty imposed.
Court ordered that no coercive steps be taken until arbitration (Reference Case No. 51/2024) is concluded, and interim order merges with final award.